Keith Marvin - FW: Bethel Road / Denton Tap Intersection TCP Phase 1(e) and Phase 1(f)
From: "Dean Dumke" <deand@JRJPaving.com>
To: "Keith Marvin" <KMARVIN@coppelltx.gov>
Date: 7/21/2010 3:59 PM
Subject: FW: Bethel Road / Denton Tap Intersection TCP Phase 1(e) and Phase 1(f)
Attachments: TCP Ph 1E & 1F 072010.pdf; TCP Ph 1E 072010.pdf
Keith,
Due to cure time on pvmt on Bethel Rd, west of Denton Tap, we will be switching traffic to the Ph 1E plan
attached on Saturday. This will allow us to continue working on the 3 median areas while we get the cure time
and curb inlets tops & throats poured and cured before we switch traffic to the outside of this area, which is
what is shown on Ph 1F submitted yesterday.
Thank you,
Dean Dumke
Sr Project Manager
#469-223-7879