ST0301A-CS100727
2010) Keith Marvin - Bethel Rd - Schedule for Project to date Page 1 From: "Dean Dumke" <deand @JRJ Paving .com> To: "Keith Marvin" <kmarvin @coppelltx.gov> Date: 7/27/2010 9:00 PM Subject: Bethel Rd - Schedule for Project to date Attachments: nevillcopier@ jrj paving. com_20100727_202547.pdf Keith, Attached you will find the schedule for the Bethel Project. I have made it as accurate to date as I could. There are dates that will continue to extend in regards to plan changes. Once you get back from vacation, I would like to sit down with you to discuss schedule and time frames we are all trying to meet. The one most important at this time is the Ph 1 section of the schedule in regards to what has happened and what is needed to reach the bonus schedule of this work and to get traffic from the Bridge to Park Ln. If you are able to check your schedule and give me a couple of time that works for you, I will work around any previous scheduled items I have already scheduled. hope you and your family enjoyed your vacation. Sincerely, Dean Dumke Sr Project Manager #469- 223 -7879 J RJ PAVING, L. P. I of 6 Ju1y201'0 August 2 01 0..:...,,. , Activity Name Duration' Start Finish Complete 2Z..., ..'4 2 1 I© 10112 Bethel Rd 072710 1461 6/14/2010 1 1/3/2011 No '..... 2 I- Ph 1 Bridge to Park ` 891 6/14/2010 10!14/2010 No ......... .... ............................ - ............ ..... .... ... .. ....... ........._ .. ........................ ......i..... .._...... ........... ..... 9 3 Demo and Instal Bridge 621 6/14/2010 1 9/7/2010 No 4 Delay in N Wall Approval 1 241 6/28/2010 7/29/2010 No i 5 1 North Wall 121 7/30/2010 8/16/2010 No 6 ,.1 South Wall 121 7/28/2010 8/12/2010 1 No .. ....... ... ...... ... ........... .. .............................. . ........ ._.. ...... .... ...... ......... ...... i 7 ;1 Utility Installation 271 6/2112010 7/27/2010 No .......... _........... 8 1 Oncor Delay H2O Connect 71 7/6/2010 1 7/1412010 1 No 9 1 Excavation /Embankment Ph 1 351 6/28/2010 1 8/13/2010 No 10 1 Lime Pvmt Subgrade 51 8/16/2010 8/20/2010 No ........................... ................................ ....... .. ....... _.. .... .. .. ......... .._..... ......... .....I........ ....... _. ........_ ......... ......._ 11 Pour 1/2 Pvmt 1 51 8/23/2010 1 8/27/2010 No _... ......... ............. _. .............. _ ....... 12 Cure Time 51 8/30/2010 9/3/2010 No 13 1 Labor Day Holiday 1 916/2010 9/6/2010 No 14 Pour 1/2 Pvmt 2 51 917/2010 9/13/2010 No .... .............. ......... ......... _ ... ............................... . ... _ ........... ..... I _ .. .................... ................. ........: ............................... : 15 Lay Asphalt Tie -in 1 10/14/2010 10/14/2010 No . ...... .. ..... ......... ......... ...... ... ... .. .. .. ......... ..3..... .. ........... ..... ... ........ .... .. ........................ 16 1 Install Future Conduit 81 9/13/2010 9/22/2010 No 17 1 Inlet Tops & Throats 3I 9/13/2010 9/15/2010 No 1 Backfill & Clean Up 5I 9/1312010 9/17/2010 No ...... ......... ...... ............................... ......... ............................... _ ......._ ............ ......... ................................ ............................... 19 Stripe Pvmt 2 9/20/2010 912112010 No ._.... ....... ..... ....................... .. _.. _ 20 Irrigation and Landscape 101 9/20/2010 10/1/2010 No 21 [3 Chateau to Denton Tap 601 711912010 10/812010 No 22 Excavtion Chat/DenTap 4I 7/1912010 1 7/22/2010 No .......... ._ ......... ! 23 : Plan Delay 5 7/22/2010 7/2812010 No 24 ,1 Haul in Additional Dirt 5I 7129/2010 8/4/2010 No 25 :1 Lime Subgrade Chat/DenTap 5I 8/5/2010 8/11/2010 No .................. 26 I Pvmt Work Mach Chat/Dent Tap ( 8I 8/12/2010 8/23/2010 No ........... .. _...._ ........... ........ . ............................... ................................ ..... .. .......................... .. ............................... ..... .. ... 27 1 Excavate E 1/2 of Chat App 2I 8/24/2010 8/2512010 No . .... . ......... _. 28 Pvmt Work 2 8/26/2010 1 8/27/2010 1 No i 29 Cure Time 5I 8/30/2010 1 9/3/2010 1 No € 30 Switch Traffic 1 9/3/2010 9/3/2010 No 2of6 ,uly 201,0 'A ugust<2Q10 Activit Name y Duration" Start Finish Gom lete' j I 31 Labor Day Holiday I 1 9/6/2010 9/6/2010 I No i 32 :: Excavation W 1/2 Chat App I 21 9/7/2010 9/8/2010 No ........ _ ................ ... ........................... ............... .................. ................ k...... .......... ............... . j 33 !`) Pvmt Work 2 9/9/2010 I 9/10/2010 No ......... ........ ..... ..... ......... _ ............ . 34 I Clean Up & Backfill Chat/Dent Tap 3 9/13/2010 9/15/2010 No I 35 Move Traffic Outsite Lns 1 9/16/2010 9/16/2010 No .............. . 36 Excavate Existing Lns Chat/Dent Tap I 3 9/17/2010 9/21/2010 No ......... . ........... ..... ..... _ ......... .... ...................... ......... .............. ......... ....... .................. ..................... 37 Lime Subgrade Middle 51 9/22/2010 9/28/2010 No .. ...... ..: _... _ _ .. _ _ . ..... _. ... ......... .... ...... 38 ! Pvmt Work 5) 9/29/2010 10/5/2010 No 39 Stamp Conc Island 3I 10/6/2010 10/8/2010 ( No 40 I Iq Aerial Crossing SS Work 1461 611412010 1/3/2011 I No ..... .......................... ................. .... .... .... ...... ........................ ... _............. 41 Drill Shafts ( 1 6/14/2010 6/14/2010 No .............. ... ._ ........ ... ..... . 42 Council Approval 1 8/10/2010 8/10/2010 No 43 I Finish Aerial Crossing Work ( 151 8/16/2010 9/3/2010 No .. .. 44 G Bethel Rd /Denton Tap Intersection ( 221 7/12/2010 8/10/2010 No ......... .................. . .. _ ...... ......... ........... _............ ........... _ .... ......... ................ .... ...... ....... ...... ............... .. ........ ...... ................... 8/10/2010 45 C— Outside Lns 101 7/12/2010 7/23/2010 No OMV 7/2312010 46 Excavate 4I 7/14/2010 7/19/2010 No a 47 Utility Work 5 7/12/2010 7/16/2010 No .. .. . .......... ..... ...... ...... 48 Pour Pvmt 2I 7/19/2010 7/20/2010 No ....... ..................... ........ ......... . ........ ... .... ............. ................... . . ........................ _ ....................._ ....... _ .... _ ................ .. . .......................... , 49 Stamp Concrete ( 2I 7/20/2010 7/21/2010 No 50 Sidewalk/Handicap Ramps 3I 7/2112010 7/23/2010 No 51 ) Inside Lns 121 7/14/2010 7129/2010 No I 7/29/2010 , 52 ) '- Excavate 3 7/26/2010 7/28/2010 No .. ..................... . ..... ......... ..... __ .. .�....... ...... .......... .. ..................... ... .................. ........ _... ........... 53 I Utility Work Tops & Bottoms 2I 7/26/2010 7/27/2010 No ..... ......... ........ ............ .............._ .. ..... _... ... .............. ...f ... .............. .. ............_ ........ ........ ... ....... _........... 54 I Pour Pvmt 3I 7/27/2010 7/29/2010 No 55 Stamp Concrete 2I 7/28/2010 7/29/2010 No 56 Oncor Street Lght & Bx Delay 111 7/14/2010 7/28/2010 No ..............._ .. ......._ ... .. .._ .. ....... ..... ................. ... ...................... ..... f .... ... .... ... ......... .. ................... ...................... _ 57 p Mels Electric Work 111 7/27/2010 8/10/2010 No ............. 8/10/2010 58 r Ped Crossings 5I 7/27/2010 812/2010 I No 59 Additional Contracted Work 5I 8/3/2010 8/9/2010 No Traffic Signal Hang TBD I 1I 8/10/2010 ( 8/10/2010 ( No .......... ... .. ................ .......... _ ..... ....... ...... ._ .. ......... .... ......... I 61 ) Ph 2 EB Bethel North Side 351 9/2112010 I 11/8/2010 No 62 Excavation 5I 9/21/2010 ( 9/27/2010 No 3of6 Activity Name Duration Start Finish Complete 63 : Lime Subgrade 5I 9/28/2010 I 10/4/2010 No 64 Pour Pvmt I 5I 10/512010 10/11/2010 No 65 Utility Tops & Throats 3F 10/18/2010 10/20/2010 No 66 I Clean Up &Backfill 1 51 10/14/2010 10/20/2010 No 67 Mels Electrical Work 5 10/21/2010 ( 10/27/2010 No 68 Irrigation & Landscape Work 8I 10/28/2010 11/8/2010 I No 6g E Ph 2 EB Bethel South Side 34I 11/412010 12121/2010 No 70 Switch Traffic I 1 11/4/2010 11/4/2010 No 71 Excavation 5I 11/5/2010 11/11/2010 No 72. Lime Subgrade 51 11112/2010 11/18/2010 No 73 I Pour Pvmt 41 11/19/2010 I 11/24/2010 No 74 ') Thanksgiving Holiday 21 11/25/2010 I 11/26/2010 No 75 Utility Tops & Throats 31 11/29/2010 12/1/2010 No 76 - Clean Up & Backfill 5I 12/2/2010 I 12/812010 No 77 Mels Electrical Work I 5I 12/612010 12/10/2010 No 78 'r Stripe Pavement 3I 12/91 1 No Irrigation & Landscape Work 8I 12/10/2010 I 12121/2010 No $p ( Final Walk with City of Coppell 9 12/2212010 1!3!2011 No 81 ) Walk Site ( 2I 12/22/2010 12123/2010 No 82 Christmas Holiday 1I 12/ 1 2 / 24/2010 No 83 I Work on Punchlist Items 4I 12/27/2010 12/30/2010 No 84 New Year Holiday 1 12/3112010 12/31/2010 No 85:11 Rewalk Punchlist Items 1 1/3/2011 113/2011 No 4of6 5of6 6of6 Activity Resource Names & %Alloc Subproject ------- - - - - - Finish Event Start --------------------------------------- ------------------------ - - - - -- ----------------------------------------------------- Cum. Original Profile - - Cum. Act. +Rem. Profile -- - Cum. Remaining Profile = Non -Cum. Original Profile P7� Non -Cum. Actual Profile