Sales Tax 09-CS100326
(8/20/2010) Keith Marvin - RE: Coppell Streets plansPage 1
From:
"Chris B. Seely" <cseely@tnp-online.com>
To:
"Keith Marvin" <kmarvin@coppelltx.gov>
CC:
"Matt Atkins" <matkins@tnp-online.com>
Date:
3/26/2010 10:09 AM
Subject:
RE: Coppell Streets plans
Keith:
April 6th at 2pm works great for us. See you then.
Have a great weekend!
Chris
Chris Seely, P.E. (TX)
Teague Nall and Perkins, Inc.
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Wednesday, March 24, 2010 5:37 PM
To: Chris B. Seely
Cc: Matt Atkins
Subject: Re: Coppell Streets plans
Chris,
We did receive the plans and specs. We will give it a priority review.
Can we go ahead and set up a review meeting for April 6th at 2:00pm to
go over our comments?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Chris B. Seely" <cseely@tnp-online.com> 3/23/2010 10:17 AM >>>
Keith:
Late yesterday, we delivered to you 2 sets of revised street plans, a
draft version of the bid book and the City comments. We are continuing
to work on the quantities to add in the plans and will have them
finished shortly. I highlighted the areas within the bid book that will
need some direction from you. These areas consist of mainly the project
bid #, dates for the bid, bid process (A+B or other), incentives, and
calendar days. The 210 calendar days listed in the book is from a
previous project. We can estimate days on our end as well.
I also need the color spec that you would like to use on the variable
height retaining walls. We took at look at the elementary school where
the existing wall is that you would like to match. Do you have a
specific spec to include?
Let me know if you have any questions or comments.
(8/20/2010) Keith Marvin - RE: Coppell Streets plansPage 2
Thanks!
Chris
Chris Seely, P.E. (TX)
Project Manager
TEAGUE NALL AND PERKINS, INC.
12160 North Abrams Road Suite 508
Dallas, Texas 75243
214.461.9867 phone
214.461.9864 fax
cseely@tnp-online.com
www.tnp-online.com