(8/20/2010) Keith Marvin - RE: Coppell Streets plansPage 1
From: Keith Marvin
To:Seely, Chris B.
CC:Atkins, Matt
Date: 4/5/2010 10:02 AM
Subject: RE: Coppell Streets plans
Chris,
Go ahead and put it together as best you can and bring it with you to the meeting. I suggest we set up the bid tab with a
section for each street. For example we would have "Section A - Hertz Road" then pay items 101A thru 144A with a
subtotal at the end of section A. These numbers then correspond to the same pay item numbers for each section. Those
items that are lump sum, we could set the quantity in the bid tab as you have shown in item #104.
Once this is all put together, I'll need to go through the plans again to verify quantities and pay items.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Chris B. Seely" <cseely@tnp-online.com> 4/5/2010 9:35 AM >>>
Keith:
We have not finished out the bid proposal sheet yet just in case you had
additional comments that we needed to revise. I can put this together
as we stand now and email it to you by tomorrow without the final
quantities. Once we meet tomorrow afternoon, we will finish it all up.
Have a great day!
Chris
Chris Seely, P.E. (TX)
Teague Nall and Perkins, Inc.
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Friday, April 02, 2010 4:02 PM
To: Chris B. Seely
Cc: Matt Atkins
Subject: RE: Coppell Streets plans
Chris,
I'm working on my plan and specification review, and I see that the Bid
Tabulation has been left out. Are you still working on that, or is it
something you can send me to look at?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Chris B. Seely" <cseely@tnp-online.com> 3/26/2010 10:05 AM >>>
Keith:
April 6th at 2pm works great for us. See you then.
Have a great weekend!
Chris
(8/20/2010) Keith Marvin - RE: Coppell Streets plansPage 2
Chris Seely, P.E. (TX)
Teague Nall and Perkins, Inc.
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Wednesday, March 24, 2010 5:37 PM
To: Chris B. Seely
Cc: Matt Atkins
Subject: Re: Coppell Streets plans
Chris,
We did receive the plans and specs. We will give it a priority review.
Can we go ahead and set up a review meeting for April 6th at 2:00pm to
go over our comments?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Chris B. Seely" <cseely@tnp-online.com> 3/23/2010 10:17 AM >>>
Keith:
Late yesterday, we delivered to you 2 sets of revised street plans, a
draft version of the bid book and the City comments. We are continuing
to work on the quantities to add in the plans and will have them
finished shortly. I highlighted the areas within the bid book that will
need some direction from you. These areas consist of mainly the project
bid #, dates for the bid, bid process (A+B or other), incentives, and
calendar days. The 210 calendar days listed in the book is from a
previous project. We can estimate days on our end as well.
I also need the color spec that you would like to use on the variable
height retaining walls. We took at look at the elementary school where
the existing wall is that you would like to match. Do you have a
specific spec to include?
Let me know if you have any questions or comments.
Thanks!
Chris
Chris Seely, P.E. (TX)
Project Manager
TEAGUE NALL AND PERKINS, INC.
12160 North Abrams Road Suite 508
Dallas, Texas 75243
(8/20/2010) Keith Marvin - RE: Coppell Streets plansPage 3
214.461.9867 phone
214.461.9864 fax
cseely@tnp-online.com
www.tnp-online.com