Keith:
I talked with Blair Baker with Texas Access (TDLR RAS) today regarding the review of our project. The rules
state that for public projects each roadway is considered a separate project (separate submittal, fees, inspection,
etc.). At the same time, you can also break the pedestrian elements cost down as well per roadway instead of a
total project cost of over $50,000. The pedestrian elements on each street are less than $50,000. We will not
have to submit the plans for TDLR review.
Regarding the construction cost to be used for TDLR fees, you were correct. The fees are based on pedestrian
elements cost only. Below is the TDLR information.
68.102. Public Right-of-Ways Projects. (New section effective February 1, 2005, 30 TexReg 382; amended
effective March 1, 2007, 32 TexReg 884)
(a) For purposes of §68.80 (fees), the estimated cost of construction for the project shall be based on the
pedestrian elements only. Construction documents submitted for review are only required to include pedestrian
elements being constructed, renovated, modified, or altered as part of the project scope."
Thanks!
Chris
Chris Seely, P.E.
(TX)
Project Manager
TEAGUE NALL AND PERKINS, INC
.
12160 North Abrams Road Suite 508
Dallas, Texas 75243
214.461.9867 phone
214.461.9864 fax
cseely@tnp-online.com
www.tnp-online.com
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C3DED7CCity...8/26/2010