ST0301A-CN100824 JRJ PAVING, L.P.
Proposed Change Order 11R
DATE: 8/24/2010
TO: City of Coppell PROPOSAL FOR : Bethel Rd II
ATTN: Keith Marvin
/ I Description j - Unit Quantity, Unit Price Total Amount 2 .-C'2 / � )
A C 6
tems
1 Remove Concrete Footing Installed (62' of Wall at Average) SF , $20.40 $8;853'.80' l
2 Excavate & Remove Concrete Footing (62' of W I at 7' average) Day 1 $1,860.00 $1,860.00 u D
3 Haul Concrete to Big City LD ,4' 1 •) $180.00 SM.''S 2-7 Q
4 Cost for Reinforcing Wall Steel (On Site and not Used) LBS 2142 $0.78 $1,670.76
Total if wall not rebuilt, Items 14 $13,104.36
Total if wall is rebuilt in new location, Items 1 -3, with item 206 on contract used to build back wall. $11,433.60
1 (-/6 q'd 0
Item 1 listed pricing is 50% of unit price of contract item 206. /
Item 4 will be deleted if the the wall is reinstalled
Should you have any questions or require additional information please feel free to call me.
Respectfully Submitted,
Dean Dumke
Sr Project Manager
1805 ROYAL LANE, STE. 107 DALLAS, TX. 75229 Page 1 of 1 PH. 214 - 466 -8340 FAX 214 - 466 -8354
JRJ PAVING, L.P.
Proposed Change Order IIR
DATE: 8/24/2010
TO: City of CoppelI PROPOSAL FOR : Bethel Rd II
ATTN: Keith Marvin
Item Description Unit Quantity Unit Price
1 Remove Concrete Footing Installed (62' of Wall at 7' Average) SF 434 $20.40
2 Excavate & Remove Concrete Footing (62' of Wall at T average) Day 1 $1,860.00
3 Haul Concrete to Big City LD 4 $180.00
4 Cost for Reinforcing Wall Steel (On Site and not Used) LBS 2142 $0.78
Total if wall not rebuilt, Items 1 -4
Total if wall is rebuilt in new location, Items 1 -3, with item 206 on contract used to build back wall
Item 1 listed pricing is 50% of unit price of contract item 206.
Item 4 will be deleted if the the wall is reinstalled
Should you have any questions or require additional information please feel free to call me.
Respectfully Submitted,
Total Amount
$8,853.60
$1,860.00
$720.00
$1,670.76
$13,104.36
$11,433.60
Dean Dumke