Wynnpage N 2&3-CS080813
(9/7/2010) Keith Marvin - RE: Wynnpage Lots 2 & 3 Storm WaterPage 1
From:
"Greg Yancey" <gregyancey@verizon.net>
To:
"'Keith Marvin'" <kmarvin@ci.coppell.tx.us>
Date:
8/13/2008 8:08 AM
Subject:
RE: Wynnpage Lots 2 & 3 Storm Water
I'm probably just overly cautious. It looked like the inlet I saw out there
last week was too far east to catch our water. I guess it will work once
it's graded.
Thanks for following up.
Gregory K. Yancey
Provident Company
(214) 215-9400 v
(214) 276-1709 f
gregyancey@verizon.net
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Tuesday, August 12, 2008 3:16 PM
To: Greg Yancey
Subject: Re: Wynnpage Lots 2 & 3 Storm Water
Greg,
The plans for that subdivision reflect the drainage area for Wynnpage. They
are placing an inlet in a common area to accept the drainage.
If you want to look at what they've got in the plans feel free to drop by
the office.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Greg Yancey" <gregyancey@verizon.net> 8/12/2008 9:05 AM >>>
Hi Keith:
Do you know if the development north of us (Ardinger property) picked up the
storm water from Wynnpage?
We had an agreement with Mr. Ardinger that the developer could re-work our
site if necessary. It looks like they've finished most of the drainage
improvements and have not contacted us about working at all on our project.
(9/7/2010) Keith Marvin - RE: Wynnpage Lots 2 & 3 Storm WaterPage 2
Thanks,
Gregory K. Yancey
Provident Company
(214) 215-9400 v
(214) 276-1709 f
gregyancey@verizon.net