WA9903-CS000509 CITY OF COPPELL, TEXAS
ADDYfION OF PUMP NO; 4
ATTFIw.
VIIJ.~t,(~E PARKWAY PUMP STATION
Project No. WA99-03; Bid No. Q-119902
CHANGE ORDER NO.. 2 (Revised)
A. INTENT OF CHANGE ORDER
Ds
The intent of this change order is to modify the provisions of the contract entered into between the City of
Coppell, Texas and Architectural Utilities, Inc., P.O. Box 11586, Fort Worth, Texas 76110, for the Addition
of Pump No. 4 at the Village Parkway Pump Station, dated December 14, 1999.
DESCRIPTION OF CHANGE
This change covers the installation of ~" tap in 36" pipe, for pressure transmitter, and the modification of the
suction piping required for Pump No. 4.
EFFECT OF CHANGE ON CONTRACT AMOUNT.
This change order will have the following effect on the cost of this project:
Item Previous Quantity Revised Unit Amount
No. Description Quantity This C.O. Quantity Unit Price of Change
5 Install W' tap h 36" pipe for 0 1 I LS. $227.00 S227.00
pressure transmitter
Field Adjustments to Suction
Piping (Pump 14o. 4)
6 0 1 1 LS. '765.00 765.00
Total: $992.00
Original Contract Amount
Amount, Change Order No. 1
Amount, Change Order No. 2
Revised Contract Amount
$346,000.00
10,684.00
992.00
$357,676.00
EFFECT OF CHANGE ON CONTRACT TIME
The contract time shall not be affected by this change order.
AGREEMENT
By the signatures below of duly authorized agents, the City of Coppell and Architectural Utilities, Inc., do
hereby agree to append this Change Order No. 2 to the original contract between themselves dated
December 14, 1999.
cop e_ lexaf"
I" ' l' 'l'
By:
Date:
Atte~
Architectural UOlifie~ Inc.
Page I of 1