ST0601-EM070105 Short Term
Intersection Activity Status Quantity Cost Total Cost
Town Center Stripe crosswalk on south side of intersection complete 1 1,550 1,550
Re- stripe stop bars all legs of intersection complete 4 300 1,200
Replace PED lights with "countdown" PED lights complete 6 300 1,800
Remove north side PED buttons /lights complete 2 30 60
Place informational signs at PED buttons complete 6 60 360
Increase walk time based on 3.5 fps complete n/a n/a n/a
Relocate PED button at SW corner Town Center /Denton Tap complete 1 30 30
Lower PED information signs to eye level complete 2 30 60
Increase all red time to 2 seconds complete n/a n/a n/a
Work w/ CISD to place articles in newspaper and on KCBY ongoing n/a n/a n/a
$5,060
Parkway Stripe crosswalk all legs of intersection complete 4 925 3,700
Re- stripe stop bars all legs of intersection complete 4 300 1,200
Replace PED lights with "countdown" PED lights ordered 8 300 2,400
Place informational signs at PED buttons complete 8 60 480
Increase walk time based on 3.5 fps complete n/a n/a n/a
Lower PED information signs to eye level complete 2 30 60
Increase all red time to 2 seconds complete n/a n/a n/a
Work w/ CISD to place articles in newspaper and on KCBY ongoing n/a n/a n/a
$7,840
Sandy Lake Stripe crosswalk all legs of intersection scheduled 4 925 3,700
Re- stripe stop bars all legs of intersection scheduled 4 300 1,200
Replace PED lights with "countdown" PED lights not ordered 8 300 2,400
Place informational signs at PED buttons complete 8 60 480
Increase walk time based on 3.5 fps complete n/a n/a n/a
Lower PED information signs to eye level scheduled n/a n/a n/a
Increase all red time to 2 seconds complete n/a n/a n/a
Work w/ CISD to place articles in newspaper and on KCBY ongoing n/a n/a n/a
$7,780
Total Short Term I $20,680
Updated 01/05/2007
Long Term
Intersection Activity Status Quantity Cost Total Cost
Town Center Provide 5' high decorative metal fence in median 1 awarded contract 1 24,000 24,000
est.completion 1/31/2007
Relocate east crosswalk / modify ramps & medians on hold 1 5,000 5,000
Add additional PED buttons on hold 3 750 2,250
Replace PED buttons w/ audible ones obtained quote 6 350 2,100
Central control unit for audible buttons obtained quote 1 2,200 2,200
Configuration unit for audible buttons obtained quote 1 300 300
Review traffic signal coordination ongoing N/A N/A N/A
$35,850
Parkway Add additional PED buttons on hold 4 750 3,000
Replace PED buttons w/ audible ones obtained quote 8 350 2,800
Central control unit for audible buttons obtained quote 1 2,200 2,200
Review traffic signal coordination ongoing N/A N/A N/A
$8,000
Sandy Lake Add additional PED buttons on hold 4 750 3,000
Replace PED buttons w/ audible ones obtained quote 8 350 2,800
Central control unit for audible buttons obtained quote 1 2,200 2,200
Review traffic signal coordination ongoing N/A N/A N/A
$8,000
Total Long Term 1 $51,8501
Other
Flashing beacons for reduced speed zone on hold 13 3,750 48,750
Signs for reduced speed zones on hold 14 90 1,260
1 Total Other 1 $50,010
(Total cost for short term, long term and other 1 $122,540
Updated 01/05/2007