ST8505-CS 870205INC.
Meeting Place:
Date:
Time:
Project Location:
CONSULTING
MINUTES OF BELT LINE ROAD
PRE-CONSTRUCTION CONFERENCE
EN ':iNEERS
Coppell City Hall - Council Chambers
FebruarYl0:00 a.m. 5, 1987
Belt Line Road (From IH635 North to Denton-
Tap Road)
Coppell, Texas
Attendees: See attached list.
Minutes:
Introduction by Mr. H. Wayne Ginn. Stated contract has been
awarded. Referenced importance of this project to City.
Introduced Kevin Peiffer as project engineer, Butch Ellison as
manager of field operations, and Randy Fleming as chief inspector.
Asked all parties involved to cooperate in completing and
finishing this project on time. Mr. Ginn offered his assistance
if required. Mr. Ginn turned meeting over to Kevin Peiffer.
Kevin Peiffer covered ground work for the project. Responsi-
bilities of Ginn, Inc. are: (1) Administer project (2) Observe
construction for conformance to plans/specifications (3) Review
payment applications and make recommendations to City of Coppell
for payment.
Intent of this meeting is not to answer technical questions.
Contractor should review plans/specifications and address
technical questions to Randy Fleming for his interpretation. All
directives for this project will be from Ginn, Inc. only unless it
is an emergency. All subcontractors should communicate through
the general contractor. City staff should communicate through
Ginn, Inc. Two main concerns on this project are: (1) Public
safety (2) maintain two-way traffic at all times, that's for all
construction, either work per this contract or work by utility
companies. Emergency telephone numbers will be provided by City
(see end of minutes).
Kevin Peiffer stated this project is a 540 calendar day project.
Notice-to-Proceed has been issued for construction to begin on or
before Monday, March 2, 1987, with completion date of Monday,
August 22, 1988. No work is permitted on Sundays per the contract
unless received written permission from the Engineer. Liquidated
damages for this project are $1000.00 per calendar day.
Kevin Peiffer stated that there will be a ribbon cutting ceremony
on Saturday, February 14, 1987. No major items of work should
commence prior to this ceremony.
17103 Preston Road · Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900
Meeting was turned over to Ed Bell to briefly outline construction
sequence proposed for this project for benefit of City staff and
utility companies to ask questions, etc.
Tom Bethune, Ed Bell Construction, reviewed construction sequence
briefly.
Kevin Peiffer asked if there were any questions from City staff or
utility companies to Ed Bell or vice versa. No response.
Bill Bettis, Lone Star Gas (Transmission), then stated that they
lowered their existing 10" line near the bank property where it
crosses Belt Line Road.
Kevin Peiffer stated to Ed Bell that verification of this utility
(10" line) would still need verified in the field to determine
whether or not it is now clear of proposed improvements.
Roy Johnson, GTE, requested being contacted by Ed Bell to verify
any conflicts that may exist.
Tom Bethune responded by stating Mike Robbins of Ed Bell was the
person to contact. He would be their Project Superintendent.
Kevin Peiffer resumed meeting and discussed procedures to be used
by Ed Bell Construction Company for this project.
Ail communication for this project shall be through Randy
Fleming (i.e. field problems, pay applications) (Shop
drawings should be sent directly to the office.)
e
No extra work or design changes can be authorized from the
field. Must come from Ginn, Inc. office, either Mr. Wayne
Ginn or Kevin Peiffer in writing.
Maintain access to all properties along project at all times.
Stay off private property without written permission from
Owner.
4. Inspection and testing: need 24 hours advance notice.
Initial testing City pays. Retest Contractor pays. On
retests, inspector will notify you in writing of failed test
results and its Contractor's responsibility to schedule retest
with lab, then provide Randy Fleming with results.
e
On water lowerings: provide 24 hours notice to City but only
after Randy Fleming verifies all the materials are on-site and
the Contractor appears ready. Contact Public Works Administra-
tion at 462-0022 (ext. 251) and ask for the Administration
Secretary. If that person is unavailable, then ask for the
Water Utilities Foreman. If they are unavailable, try back
later. Do not leave messages with the receptionist scheduling
shutoffs. Must schedule with designated individuals stated
herein.
0
e
Only City to operate water valves.
Traffic signals: submit relocation requests in writing to
Randy Fleming with date relocation is needed by and details.
Engineer will coordinate with signal person and follow-up
correspondence verifying this request completed.
Detours/Barricades/Switching traffic: Need plan submitted one
week prior for review by Randy Fleming prior to any work.
Keep City (Police and Fire) informed on dates of opening
detours.
Police Lt. Charles W. Daniel interjected that they would like to
be involved in the review of detours and barricades along with
Ginn, Inc. before work commences on them. To contact him to set
up a meeting for this, call 462-1580 or 462-1144. Kevin Peiffer
responded that this would not be a problem and that we would hold
a meeting on-site in future when issue is addressed.
10. Construction easement at lake was granted by Texas Utilities
Generating Company for whatever reasonable distance is needed
out into the lake in order to build cofferdams needed for
storm drainage construction. Texas Utilities Generating
Company has shown their cooperation to City by doing this and
we ask Contractor to do the same for them by controlling their
own people and keeping trash and debris out of the lake. This
will not be tolerated.
11. Concrete cylinders: Taken at Randy Fleming's request by
Contractor and witnessed by Randy Fleming. Lab will pick.
Interim time care of cylinders is responsibility of the
Contractor.
12. Payment procedure: Submit by 10th for work through last day
of previous month. Paid by City within 30 days thereafter.
Only pay for work meeting plans and specifications.
13. Submit cash flow and construction schedules prior to March 2,
1987, start date. Submit revised updated construction
schedules each month with pay application per Division I of
specifications.
Kevin Peiffer asked if there were any questions. None. Kevin
Peiffer then asked Ed Bell where their intended source of water is
for this project. Do they need a City water meter? What is the
intended use for this water (ie. achieve density, concrete mix,
etc.)?
Ed Bell said that they would use City water for some work and also
use their well water on their property for the concrete.
Kevin Peiffer stated that a sample would be needed of their well
water and the test results presented to our office for review.
The City will also need to certify and approve Ed Bell's water
meter they intend to use for this project.
Kevin Peiffer stated we have received some shop drawings and
apologized for apparent slow response on returning them. Due to
a suspended contract and efforts needed to secure construction
easement at the lake first, the review of these drawings is not
yet complete. Response time in future will be better and they
will be returned in a more timely fashion.
Kevin stated shop drawings are required on all cast-in-place and
pre-cast structures. No payment shall be made or inspections done
on items that have not had shop drawing review and comments on.
Kevin Peiffer asked Tim Sullivan if he has acknowledged the
Notice-to-Proceed yet. Tim replied no.
Randy Fleming stated Ed Bell is responsible for as-built drawings,
submittals, etc., per the contract and will be required as part of
contract close-out prior to final payment.
Kevin asked if anyone had questions.
11:00 a.m.
None.
Meeting adjourned at
After meeting adjourned the following events occurred:
Payment application form given to Ed Bell Construction Company.
Following emergency telephone numbers and names were provided.
Ed Bell Construction Co. (main office)
Mike Robbins, Project Superintendent (home)
Tom Bethune, Manager Contract Admin. (home)
214-556-1475
214-850-2753
214-539-9037
Coppell City Hall (main #)
214-462-0022
Police, Fire, & Ambulance
911 (if using local phone only)
214-462-1144 (cellular phones
or outside (462) C0ppell area)
Good only until April 1, 1987.
After April 1, 1987, there will
be a new (462) number to call.
Is not being released publicly
until April 1, 1987.
Public Works Department
214-462-0022 Ext 251 M-F 8a.m.-5p.m.
214-462-1144 Weekends or evenings
ATTENDANCE ROLL
A. J. Johnston
Tom Bethune
Mike Parent
Mike Robbins
Tim Sullivan
B.D. Harkins
Mr. Thomas
Johnny Heine
Roy Johnson
Ward Hendrickson
Glenn Fabian
Freeman Jarrell
Henry Myatt
Michael McCormack
Mark Person
Jimmy Clack
Randy Rogers
~[eve Goram
Steve Morton
Shohre Daneshmand
Lt. C. W. Daniel
Wayne Ginn
Butch Ellison
Randy Fleming
Kevin Peiffer
Ed Bell Construction Co.
Ed Bell Construction Co.
Ed Bell Construction Co.
Ed Bell Construction Co.
Ed Bell Construction Co.
B & J Excavating
B & J Excavating
Mel's Electric
General Telephone
SW Bell Telephone
Texas Power & Light Co.
Texas Utilities
Stripe-A-Zone
Pavestone Company
Stimson
Rogers and Clack
Rogers and Clack
City of Coppell
City of Coppell
City of Coppell
City of Coppell Police Dept.
Ginn, Inc.
Ginn, Inc.
Ginn, Inc.
Ginn, Inc.