CIP Utility Meeting
May 25, 2004 — 2:00 p.m.
I. City Contacts
Keith Marvin, P.E. Civil Engineer (972- 304 -7044) — in -house designs, permit review & approval
Suzan Taylor — CIP Coordinator (972- 304 -7019) — plans, construction schedules, utility meetings
Garreth Campbell — Construction Inspector (972- 304 -3685)
Larry Davis — Construction Inspector (972- 304 -3684)
Rick O'Dell — Construction Inspector (972- 304 -7090)
Engineering Fax No. — 972 - 304 -3570
Streets Telephone No. — 972 - 462 -5150
Water Utilities Telephone No. — 972 - 462 -5155
II. Status of Proposed City Construction Projects
STREETS
Project: ST 93 -01
Name: Sandy Lake Road (Kimbel Kourt to East City Limits)
Design Engineer: Jacobs Civil
Scope: ± 4300 L.F. — Reconstruct 2 -lane asphalt to 4 -lane divided roadway with drainage
improvements
Status: Design is 99% complete. Updated plans available during this meeting.
Right -of -Way: Right -of -way acquisition is complete.
Utilities: February 4, 2004 follow -up letter regarding any new facilities constructed since 2002
sent. Utilities need to initiate relocations. Eight horizontal/vertical control monuments have been
set.
UTILITY COMPANY FACILITIES WITHIN RELOCATION EST.
PROJECT LIMITS COMPLETION DATE
AboveNet No facilities (09- 16 -02)
AT &T Local Network Services No facilities (09- 18 -02)
Brazos Electric Company No facilities (02- 11 -04)
Comcast
CoSery No facilities (09- 30 -02)
Explorer Pipeline
McLeod No facilities
Oncor Electric
OnFiber Carrier Services
Qwest Communications No facilities (10- 03 -02)
SBC No facilities (09- 23 -02)
1
UTILITY COMPANY FACILITIES WITHIN RELOCATION EST.
PROJECT LIMITS COMPLETION DATE
TXU Communications Services
TXU Gas
Verizon Communications
Dallas Water Utilities No conflicts
City of Irving No conflicts
360networks Inc. No facilities (09- 19 -02)
Estimated Construction Start: July /August 2004
Project: ST 99 -05
Name: Bethel Road I (West City Limits to Freeport Parkway)
Design Engineer: Tran Systems
Scope: ± 6500 L.F. — Reconstruct 2 -lane asphalt to 4 -lane divided roadway with drainage and
channel improvements. May construct the roadway and channel as separate projects due to the
USACE 404 permitting process.
Status: Design is 90% complete. 80% plans have been provided to utility companies.
Right -of -Way: Right -of -way acquisition for the roadway is underway. Drainage easement
acquisition for the channel has not started. Some utilities may conflict with the proposed channel.
Will need right -of -way at the box culvert — part of Bethel II acquisition.
Parcel 1 Fellowship of Las Colinas ACQUIRED
Parcel 3 Walter Hogg Partnership Appraisal process started on 04 -27 -04
Parcel 4 DFW Airport June 8, 2004 City Council
Parcel 5 Gulf United Industries ACQUIRED
Parcel 6 Texas Dugan Limited Partnership Corner Clip
Parcel 7 Hillwood Investment Properties ACQUIRED
Parcel 8 Minyards Food Store ACQUIRED
Parcel 9 Texas Dugan Limited Partnership Corner Clip
Parcel 10 City of Coppell ACQUIRED
Parcel 11 Texas Dugan Limited Partnership Corner Clip
Utilities: Utilities can initiate relocations on the north side of the roadway (from east of Royal
Lane to east of Freeport Parkway). Utilities may locate facilities under the proposed roadway on
parcels that have not been acquired (from east of Royal Lane to east of Freeport Parkway) or wait
until the right -of -way has been acquired to relocate facilities.
Oncor — coordinate with the Town of Grapevine on construction of Bethel/Bass Pro Roads.
UTILITY COMPANY FACILITIES WITHIN RELOCATION EST.
PROJECT LIMITS COMPLETION DATE
AboveNet 05 -12 -03 permit approved Utilities relocated
AT &T Local Network Services 05 -12 -03 permit approved Utilities relocated
2
UTILITY COMPANY FACILITIES WITHIN RELOCATION EST.
PROJECT LIMITS COMPLETION DATE
Comcast
CoSery
Explorer Pipeline Consultant working with
Explorer to minimize
length of relocation
McLeod
Oncor Electric
OnFiber Carrier Services
Qwest Communications 05 -24 -02 - submitted plans:
coordinate relocation with
360networks Inc.
SBC 05 -12 -03 permit approved Utilities relocated
360networks Inc. 12 -02 -02 - submitted plans:
(Touch America) coordinate with Qwest
TXU Communications Services
TXU Gas
Verizon Communications 06 -05 -03 - submitted plans:
will wait until right -of -way
is acquired to relocate
Estimated Construction Start: 4 Quarter 2004
Project: ST 99 -02A
Name: Sandy Lake Road (SH 121 to Coppell Road N.)
Royal Lane (Northpoint to Sandy Lake)
Design Engineer: Teague Nall and Perkins
Scope: ± 6500 L.F. — Reconstruct 2 -lane asphalt to 4 -lane divided roadway with drainage and
channel improvements. - ±1300 L.F. - Construct two additional lanes to make Royal Lane a 4-
lane divided roadway
Status: Design is 80% complete. Initial contact was made with utilities in June to August 2001
to determine location of facilities. 80% plans were sent to utility companies on October 31, 2003.
Right -of -Way: Preparation of right -of -way and easement documents should be complete by June
2004.
Utilities: Relocations not initiated.
Estimated Construction Start: 4 Quarter 2004
Project: MA 02 -03
Name: Brick Paver Replacement Program
Design Engineer: In -House
Scope: Remove and replace brick pavers with alternate material along MacArthur Boulevard,
(DeForest to Belt Line Road). Seven possible intersections.
3
Status: Design is 85% complete. The City is reviewing options for the replacement material
Plans were sent to utilities on April 20, 2004.
Right -of -Way: In City of Coppell right -of -way.
Utilities:
UTILITY COMPANY FACILITIES WITHIN RELOCATION EST.
PROJECT LIMITS COMPLETION DATE
AboveNet No facilities (05- 05 -04)
AT &T Local Network Services No facilities (04- 27 -04)
Comcast
Explorer Pipeline
McLeod No facilities (04- 26 -04)
Oncor Electric
OnFiber Carrier Services
SBC Communications
TXU Communications Services
TXU Gas
Verizon Communications No facilities (04- 27 -04)
Estimated Construction Start: 3 Quarter 2004
WATER
Project: WA 00 -02
Name: Golden Triangle Mobile Home Park
Design Engineer: Pacheco Koch Consulting Engineers
Scope: ± 900 linear feet of 8" water line and 3 fire hydrants. The water line is within utility
easements in the mobile home park and Alford Media property.
Status: June 8, 2004 City Council & June 15, 2004 County Commissioner's Court. Plans were
provided to utility companies during Dallas County's monthly utility meeting in May 2003.
Right -of -Way: Land rights acquisition is complete.
Utilities: Gas easements throughout the mobile home park.
Estimated Construction Start: June /July 2004
Project: WA 01 -01
Name: SH 121 Water Line
Design Engineer: Birkhoff, Conway & Hendricks
Scope: ± 8800 linear feet of 12" water line and appurtenances. The majority of the water line is
within SH 121 right -of -way and a small portion is within utility easements and City right -of -way.
Status: Design is 90% complete. Plans available during this meeting.
Right -of -Way: Three to four parcels — land rights acquisition has been initiated.
Utilities: Design engineer is making contact with the utilities located inside of the SH 121 utility
corridor to try and determine any conflicts with the proposed water line.
Estimated Construction Start: 4 Quarter 2004
4
SEWER
Project: SS 99 -01
Name: DeForest and Sandy Lake Force Main — Line "D"
Scope: ± 8700 linear feet of 30" force main by directional drilling. Part of the force main is
within MacArthur right -of -way and part of the force main is within existing and proposed utility
easements
Status: Construction Contract awarded during the May 11, 2004 City Council meeting. Plans
provided during the November 13, 2003 utility meeting.
Utilities:
Estimated Construction Start: June 2004
Project: SS 02 -01
Name: Service Center Sanitary Sewer Line
Design Engineer: In -House
Scope: ± 1800 linear feet of 18" sewer line along the DART railroad line from Coppell Road to
Grapevine Creek.
Status: Construction Contract awarded during the May 11, 2004 City Council meeting. Plans
provided to utilities in February 2004, follow -ups in March and April.
Right -of -Way:
Utilities:
UTILITY COMPANY FACILITIES WITHIN RELOCATION EST.
PROJECT LIMITS COMPLETION DATE
AboveNet no conflicts (02- 24 -04)
AT &T Local Network Services no conflicts (02- 17 -04)
Brazos Electric Company no facilities (02- 11 -04)
Comcast no conflicts (03- 30 -04)
CoSery no conflicts (02- 13 -04)
Explorer Pipeline verbal contact
McLeod no conflicts (02- 18 -04)
Oncor Electric no conflicts (04- 23 -04)
OnFiber Carrier Services
Qwest Communications utilities in area (03- 04 -04)
SBC no conflicts (03- 02 -04)
TXU Communications Services
360 Networks Inc. No conflicts (04- 01 -04)
TXU Gas
Estimated Construction Start: June 2004
TRAFFIC
Project: TR 03 -01
Name: MacArthur / Belt Line Traffic Signal
Design Engineer: In -House
Scope: Replace cabinet and foundations, loops, rewire, install red LEDs and replace mast arms to
accommodate left turn signals.
Status: Design is 75% complete. Plans available during this meeting.
5
Right -of -Way: NA
Estimated Construction Start: 3r Quarter 2004
III. Permits
Utility companies need to complete and submit a Right -of -Way permit for utility relocations that
are required on municipal projects.
IV. Update Utility Company Contacts
The contact list is attached. Please correct as necessary and return to me.