2005_08_23 T H E • C 1 T Y O F COPPELL A S , 8 CIP Utility Meeting August 23, 2005 @ 2:00 p.m. File No. 0816 I. City Contacts Keith Marvin, P.E. Civil Engineer (972- 304 -7044) — in -house designs, permit review & approval Suzan Taylor — CIP Coordinator (972- 304 -7019) — plans, construction schedules, utility meetings Garreth Campbell — Construction Inspector (972- 304 -3685) Larry Davis — Construction Inspector (972- 304 -3684) Rick O'Dell — Construction Inspector (972- 304 -7090) Engineering Fax No. — 972 - 304 -3570 Streets Telephone No. — 972 -462 -5150 Water Utilities Telephone No. — 972 - 462 -5155 II. Status of Proposed City Construction Projects STREETS Project: ST 99 -02A Name: Sandy Lake Road (SH 121 to Coppell Road N.) Royal Lane (Northpoint to Sandy Lake) Design Engineer: Teague Nall and Perkins Scope: ± 6500 L.F. — Reconstruct 2 -lane asphalt to 4 -lane divided roadway with drainage improvements. ±1300 L.F. — Construct two additional lanes to make Royal Lane a 4 -lane divided roadway Status: Design is 99% complete. Advertise: September 2005 Open Bids: October 2005 Construction Start: November 2005 Right -of -Way: Acquired Utilities: Need to initiate and complete relocations. UTILITY COMPANY FACILITIES WITHIN PROJECT LIMITS STATUS AboveNet Joint trench — AT &T taking lead AT &T Local Network Services Manhole @ intersection of Royal /Sandy Lake Qwest Communications _ Joint trench / submitted relocation plans 360networks Inc. Started relocations TXU Electric Delivery Submitted relocation plans Verizon Communications 06 -10 -04 — submitted relocation plans waiting on right -of -way acquisition Atmos Gas Have facilities — no relocation plans submitted 1 UTILITY COMPANY FACILITIES WITHIN PROJECT LIMITS STATUS Comcast No relocation plans submitted Cosery NONE Explorer Pipeline NONE McLeod USA NONE Onfiber Carrier Services NONE SBC Communications NONE THE BETHEL ROAD I PROJECT WILL BE BID AND CONSTRUCTED IN CONJUCTION WITH THE CITY OF GRAPEVINE'S BASS PRO ROAD (WEST CITY LIMITS OF COPPELL TO SH 121) Project: ST 99 -05 Name: Bethel Road I (West City Limits to Freeport Parkway) Design Engineer: TranSystems Scope: ± 6500 L.F. - Reconstruct 2 -lane asphalt to 4 -lane divided roadway with drainage and channel improvements from Freeport Parkway to north of Bethel Road. A short section of 8" sewer line will be constructed with this project -it is located behind CiCi's Pizza and should not impact any existing utilities. Status: Consultant is working on the final plans. Right -of -Way: Right -of -way acquisition for the roadway is complete. No additional right -of -way is ' required for the channel and box culvert construction. Channel plans adequate for utility relocations will be distributed during this meeting. Drainage Easement: Acquisition of the two drainage easements immediately north of Bethel Road has not started - this should not impact utility relocations. Utilities: Need to initiate relocations once the trees have been removed. UTILITY COMPANY FACILITIES WITHIN PROJECT LIMITS STATUS AboveNet Utilities relocated AT &T Local Network Services Joint trench — - 05 -12 -03 permit approved Utilities relocated SBC Communications Utilities relocated Qwest Communications Joint trench 10 -15 -04 - submitted relocation plans 360networks Inc. Relocations started Explorer Pipeline 10 -12 -04 - agreement executed no relocation required Verizon Communications 06 -05 -03 - submitted relocation plans: will wait until right -of -way is acquired to relocate Comcast NONE CoSery NONE OnFiber Carrier Services TXU Electric Delivery Atmos Gas 2 Bass Pro Road UTILITY COMPANY FACILITIES WITHIN PROJECT LIMITS STATUS Explorer Pipeline Easement from DFW Airport Atmos Gas NONE TXU Electric Delivery Pole line on north side of the road will need to be moved. Plans sent to Richard Brewster. Would like to leave facilities in place near the SH 121 crossing as not to have to cross SH 121 again. Will need to look at sidewalk placement and the poles. Underground on south side of roadway with an above ground crossing over Cottonwood Verizon Branch. Robert Martinez. Will send a new set of plans to his office. He will outsource to John Powell. SBC Communications NONE CoServe NONE Comcast Warren Fyffe AT &T Local Network Services Mike Crawford Waiting on their review of our plans. AboveNet (Metromedia Fiber) Response should be by 8/12/05 360 Networks NONE Qwest Scott Whaley OnFiber Carrier Services NONE Estimated Construction Start: 1st Quarter 2006 Project: ST 00 -03 Name: Coppell Road (Cooper Lane to Sandy Lake Road) Design Engineer: Huitt Zolllar Scope: ±1900 L.F. - Coppell Road will be two -lane, undivided, 34' to 37' back -to -back with improved drainage. Roadway is being constructed within the existing right -of -way. Status: 60% plans provided during 10 -41 -04 meeting. Right -of -Way: Acquisition has not started. Only one parcel of right -of -way will be acquired. Utilities: Relocations have not been initiated Estimated Construction Start: 3 Quarter 2006 3 Project: ST 03 -01 Name: Bethel Road II (Loch Lane to Denton Tap) Coppell Road (Cooper Lane to Bethel Road) Design Engineer: Freese & Nichols Scope: ±5400 L.F. - Bethel Road will be two -lane, undivided, 28' back -to -back with improved drainage. The existing culvert at Stream G -1 will be replaced with 4 - 10' x 6' box culverts. ±1900 L.F. - Coppell Road will be two -lane, undivided, 34' back -to -back with improved drainage. The existing culvert at Stream G -1 will be replaced with 4 - 10' x 8' box culverts. Signal improvements at the intersections of Coppell Road and Denton Tap. Hike and bike trail and sidewalk improvements. Status: 60% plans provided during 10 -21 -04 meeting. Right -of -Way: Legal description and plats are complete — acquisition has not started. Utilities: Relocations have not been initiated Estimated Construction Start: 1st Quarter 2007 WATER Project: WA 97 -01 Name: Denton Tap Water Line (Airline Road to Bethel Road) Design Engineer: Birkhoff, Conway & Hendricks Scope: ± 4050 linear feet of 16" water line and appurtenances. The majority of the water line is within Denton Tap Road right -of -way. The water line will be installed along the west right -of -way from Airline Road to Southwest and within the median from Southwest to Bethel Road. Status: Design is 100% complete. Advertise: August 2005 Open Bids: September 2005 Construction Start: October 2005 Utilities: No relocations required, however there are Atmos 3" and 10" gas lines, a Comcast fiber optic line, and telephone lines in close vicinity to the proposed water line. TRAFFIC ST 97 -03 TR AND TR 03 -01 WILL BE BID TOGETHER. Project: ST 97 -03 TR Name: MacArthur / Bethel School Traffic Signal Design Engineer: In -House Scope: Install traffic signal Status: Final plans are under review Right -of -Way: NA Estimated Construction Start: 1S Quarter 2006 4 Project: TR 03 -01 Name: MacArthur / Belt Line Road Traffic Signal Design Engineer: In -House Scope: New cabinets, foundations, mast arms to accommodate left turn signals, rewire, install red LEDs Status: Final plans are under review Right -of -Way: NA Estimated Construction Start: 1 Quarter 2006 III. Permits Utility companies need to complete and submit a Right -of -Way permit for utility relocations that are required on municipal projects. Utilities may want to review previously approved permits to note the new location of the relocated utilities — this will help with utilities trying to relocate in the same location. IV. Update Utility Company Contacts The contact list is attached. Please correct as necessary and return to me. 5 ITY LIMIT Q\.,.......>1... _______,________ O� N Y _ DENTON COUNTY. Allikil4 / IA I• •1 t7, T tv isso .._ AII. z z ED _ U W >_,._ UU ' ` Ir III 9 N Z �� m o 0 � m cnOZ v ¢ h� ` co oNN rii7 /� A. - C) I mil OD i+ -1 CO + cn cn O L- O 25: F:, ; :cl. r 0 o 0 ,m m wo p c) O co 1 0 0 c �0 oy� 0000�g C o N(D n 0 O CCl) - p c' G p C O SANDY LAKE RD. �j _ m r - r o U+ ( r Z n N ` 1 '� d m T O v O? o n 3 T° , °' m D - id ��j \ ' 7 ` / � I I � ' I �I'' f ll y 1��� E ' ° - `-° m -- c> N Q° in I I J/ \ IUUU 0 O O "O O O ai fD A 7 O.'O p O O T N C c = NORTHPOIMr 3 W p T T c `� rn m v c Oo ° r m N 0 n r O v o o O a N N N n 7 3 N 5 - N a N T "O j (D N O N W N p fl- C "O rig ° ° v� o p p a 0 6 v ° o m n m - . m O m m O T O m 73 (i e c = 0 m O o v D o to cn 'IT 0 f G o r o o m-- Z a .� a) p� SU {n P- N N av co :3._ 7r O p X O N N p o A >- N I— N - r U Co o °. N SU r BETNEL RD. m a m C7 0 0 m C) 0 v o W O 7 o n Q N N cn d n n N Cl_ m m m Q a ° O U m m cD o v co on 70 73 7J O O o l A n v CD t11 N N 0 7� O. a a o m o 0 CD O. X .....›...„..........„--„,„ 6, 0 0 0 n m n v v v * a CO m o 5 o CO m o O IJ v m m 0 o r i 41 I' k z �' , j 1 M i 'N9 Ai i ‘N i C� H 4- Z-- �J Q N 1 cc, t" J E_ v LLB, 2 W .\.) _a, s 0- o • z ,‹, __---_-___ Q .. ...____k , i21 C3 \'' , ._ f: _r‘ -z x U z H w w C NI y 4 ° 4 .1/4,) v , 0 • , r_ii 6 3 r'. i .,t v _iT t -_i ,, c 1 4 az 0-1 ,.., = D ' —n 'k j r: a , ...d rsi t 0 0 - (1 1 :( 3 7t ( D ij -i E. w 0 ' o,) o . H d , �� `� `� CA \ - E. V ti --+ N r i v i ∎) l � o OT GA M z z O r � o � � a � ° N. k w0' : z O M V z W W o a 4 's a o 0 U U N • H H� 4 k oti � � CV \ Streets LIMIT ` Project: ST 99 -02 A Name: Sandy Lake (SH 121 to Coppell Road N.) (Royal Lane to Sandy Lake) O EI1) Den: Teague Nall & Perkins � Scope: t 6500 L.F. - Reconstruct 2- Lane Asphalt to 4 -Lane Divided Concrete Road with Drainage DENTON COUNTY DENTON COUNTY Improvements 1 I• • • 1 .......................... DALLAS COUNTY + 1300 L.F. - Construct 2 additional lanes to make Royal Lane a 4 -lane divided roadway _F \ ' � �L © Est. Construction Start: November 2005 I I I I I WI Y _ A. \� 4 *..?0 vN _ ; I Project: ST 99 -05 >- ' Name: Bethel Road I (W. City Limits to Freeport Pkwy.) z ro� ��� •% Design: TransSystems Funding: CIP o a r 0 M 3 Scope: ± 6500 L.F. - Reconstruct 2- Lane Asphalt to 4 -Lane Divided Concrete Road with Drainage v I \� C `O \ and Channel Improvements z ¢ ' (v �, ` I �` O _\ Est. Construction Start: 1st Quarter 2006 ce J �, 11111 1 C , �r I �I , I I a �; ce A v Rt Ri� 0 _� \Vt2 Project: ST 00 -03 ,r, L J II 1 � '� I I Name: Coppell Road (Cooper Lane to Sandy Lake Road) L C as I _ O I I � Design: Huitt Zollar Funding: CIP 1 _ O Scope: ± 3600 LF. - Reconstruct 2- Lane Asphalt to 2 -Lane Concrete Road with Drainage SANDY LAKE RD. 1 ID I \ n �� Improvements r � I I I I ' Est. Construction Start: 3rd Quarter 2006 i I DOT- a 4 � � � _ ^, • Project: ST 03 -01 1 I� Name: Bethel Road II (Loch Lane to Denton Tap) NORTHPOINT �n n 0 !0 _ 1 �� �� r f / Coppell Road (Cooper Lane to Bethel Road) I � � �� t Design: reese &Nichols Funding: CIP '' ® l® n +F 5400 L.F. Reconstruct 2- Lane Asphalt to ::: Concrete Road with Drainage Concrete Road with Drainage II z� l l� 6 - rT - \ , Improvements s , , l/ 4 k n � 1j ^�) 0 - Est. Construction Start: 1st Quarter 2007 AirCri Ili BE RD. 1101 ...,. � �•• ' a 1 a C ^ . © ► U i • =3-- ° e vim ,, ' \�J BELT Oil- � �1t 33 ° a - Water ■ 1 COPP IN > TY ' 44-1 S D z Project: q Name: D nt on Water Line (Airline Road to Bethel Road) U o O Design: Birkhoff Hendricks & Conway Funding: RB U Scope: ± 4050 L.F. of 16" Water Line i z a Est. Construction Start: October 2005 a J CC CE a a A Traffic Project: ST 97 -03 TR ‘11. \ Name: MacArthur /Bethel School Traffic Signal N Design: In -House Funding: IMF Scope: Install Traffic Signal Est. Construction Start: 1st Quarter 2006 Project: TR 03 -01 <IM Name: MacArthur In -House / Belt Line Funding: Traffic Signal IMF IT 2 \ Design: Scope: Replace Cabinet & Foundations, Loops, Rewire, Install Red LEDs and Replace Mast Arms to Accommodate Left Turn Signals T H E• C 1 T Y• O F Est. Construction Start: 1st Quarter 2006 COPPELL ....... �� Location Map - Proposed Construction Projects x A S 1 8 q August 23, 2005 CIP Utility Meeting