Sales Tax 09-CN101021CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Sales Tax 2009 Street Reconstruction Project
Dobecka Drive (Tax 2009)
CONTRACTOR: Conatser Construction
OWNER: City of Coppell
CHANGE ORDER NO.: One (1) DATE: October 12, 2010 Page 1 of 1
1. This change allows for the repair of various sections of failed sewer line.
Item Description
ADD: 1. Remove and replace
6" PVC sewer line.
Total Additions:
$4,800.00
Previous contract amount $297,835.00
Net increase in contract amount $4,800.00
Revised contract amount $ 302,635.00
Cumulative increase in TOTAL change order amount (Percentage) 1.6%
Net increase in contract time of completion 0
Revised Contract time of completion 120 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.
r 10'14,10
R ommended y City Engineer Date
Agreed to by ConoWctor Date
Acceptid by City Date
Quantity
Unit
Unit Price
Total
100
LF
$48.00
$4,800.00