Sales Tax 09-CN101021CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Sales Tax 2009 Street Reconstruction Project Dobecka Drive (Tax 2009) CONTRACTOR: Conatser Construction OWNER: City of Coppell CHANGE ORDER NO.: One (1) DATE: October 12, 2010 Page 1 of 1 1. This change allows for the repair of various sections of failed sewer line. Item Description ADD: 1. Remove and replace 6" PVC sewer line. Total Additions: $4,800.00 Previous contract amount $297,835.00 Net increase in contract amount $4,800.00 Revised contract amount $ 302,635.00 Cumulative increase in TOTAL change order amount (Percentage) 1.6% Net increase in contract time of completion 0 Revised Contract time of completion 120 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. r 10'14,10 R ommended y City Engineer Date Agreed to by ConoWctor Date Acceptid by City Date Quantity Unit Unit Price Total 100 LF $48.00 $4,800.00