ST0301A-CN100803 (2)CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Bethel Road II (ST 03 -01A) CONTRACTOR: JRJ Paving, L.P. OWNER: City of Coppell CHANGE ORDER NO.: One (1) DATE: July 30, 2010 Page 1 of 2 1. Approval to close two lanes each direction along Denton Tap Road for a period of up to 40 calendar days in accordance with the approved Council Resolution. This closure is necessary for the completion of the intersection improvements associated with the Bethel Road Project. 2. Providing for an early completion incentive of $2,000 per calendar day for completion in less than 30 calendar days. Maximum incentive established at $20,000. 3. Providing for liquidated damages in the amount of $2,000 per calendar day for any lane closures along Denton Tap that extend beyond 40 Calendar Days. 4. Definition of "early completion" is all lanes of Denton Tap, and all lanes of East Bethel Road open to unimpeded traffic. 5. Providing for payment of additional items listed below as necessary for the completion of this portion of the project. Item Description Quantity Unit Unit Price Total ADD: 1. Additional "high early" concrete for Denton Tap Paving 2. 18" Stop Bars 1 LS 125 LF 2,000.00 $2,000.00 5.18 $647.50 3. Raised Pavement 104 EA 8.25 Marker, Type I -C 4. Early Completion 10 Day 2,000.00 Incentive ** Total Additions: * *Early completion incentive varies to a maximum of $20,000 as described above $858.00 $20,000.00 $23,505.50 Previous contract amount Net increase in contract amount $1,969,019.05 $23,505.50 Revised contract amount $ 1,992,524.55 Net increase in contract time of completion 0 Revised Contract time of completion 270 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. by C,ikq'Engineer Date Iz v l- Agreed to Contractor Date Accept by City Date