RE: Southwestern Boulevard Reconstruction, Project #ST 07 -01
Final Acceptance
Dear Mr. Oyen:
Representatives of the City of Coppell have confirmed a final inspection of paving and utilities
for the referenced project. The two -year maintenance agreement and record drawings have been
received. Maturity on the agreement will be two years from the date of this letter.
A follow -up inspection of the facilities will be conducted prior to the lapse of the two -year bond
period. If any punchlist items are noted at that time, you will be contacted to make repairs. Thanks
for your cooperation during the course of this project.
Sincerely,
� / �
Rick O'Dell Keith R. Marvin, P.E.
Construction Inspector Project Engineer
Office Phone: (972) 304 -7090
Fax: (972) 304 -3570
cc: Ken Griffin, P.E., Director of Engineering & Public Works
Glenn Hollowell, P.E., Asst. Director of Public Works
LH Lacy Company
Jorge Rodriguez, P.E., Halff Associates
A FAMILY COMMUNITY FOR A LIFETIME
255 PARKWAY * P.O. BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * WWW.COPPELLTX.GOV