ST0001-CN021022 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: CREEKVIEW DRIVE PROJECT # ST 00 -01 CONTRACTOR: INFRASTRUCTURE SERVICES, INC. OWNER: CITY OF COPPELL CHANGE ORDER: # 4 DATE: 10/22/02 ADD: Item Quantity Unit Description Unit Price Total Price New 1 LS Disposal of excess dirt not shown on 58,075.00 58,075.00 construction plans New 1 LS Disposal of excess dirt associated with the 14,125.00 14,125.00 sidewalk design not shown on construction plans New 1 LS Extra mobilizations due to phasing not 18,504.00 18,504.00 shown on construction plans New 1 LS Loss of efficiency associated with required 18,092.00 18,092.00 phasing New 1 LS Installing and maintaining temporary roads 9,792.00 9,792.00 due to phasing New 1 LS Maintaining barricades due to required 7,440.00 7,440.00 phasing TOTAL ADDITION $126,028.00 TOTAL CHANGE ORDER #4 5126,028.00 Original Contract Amount $1,040,811.47 Contract Amount including Change Order #1 (- $18,050) $1,022,761.47 Contract Amount including Change Order #2 ($1,459.13) $1,024,220.60 Contract Amount including Change Order #3 (517,180.15) $1,041,400.75 Total Change Order #4 $ 126,028.00 Revised Contract Amount $1,167,428.75 Change Order #4 Pagel Net Increase in Contract Time of Completion 102 Days Revised Contract Time of Completion 267 Days The contractor hereby accepts this contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason for this revision to the Contract. �,,.� l 0 • Z z • �.. Recommended y ity Engineer Date 1/ - /'f 0/17L Accepte I Owner Date Agreed to b Con ' . or Date Change Order #4 Paae2