ST0004-CN010824
August 24, 2001
R.J. Evans, Jr., Vice President
Quantum Contracting, Inc.
P.O. Box 430
Rockwall, TX 75087
RE: Freeport Parkway Reconstruction Project ST 00-04
Dear Mr. Evans:
Attached is Change Order #1 for the referenced project. Please sign and returned
one original to me.
If you have any questions feel free to call Larry Davis, the Construction Inspector
on this project, at (972) 304-3685.
Sincerely,
Kenneth M. Griffin, P.E.
Director of Engineering/Public Works
cc: Larry Davis, Construction Inspector
st00-04\changeord1ltr
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Freeport Parkway Reconstruction Project # STO0-04
CONTRACTOR: Quantum Contracting, Inc.
OWNER: City of Coppell
CHANGE ORDER NO.: 1 DATE: 8/23/01
Item Description Quantity Unit Unit Price Total
Reconstruct and shorten median nose at Gateway Crossover
ADD:
Sawcut, demolish existing median nose 1 LS 1,400.00 $1,400.00
and brick pavers. Install new curb and
gutter subgrade treatment. Concrete
paver base and brick pavers. Shorten
median nose by +1- 10 feet.
Sawcut, demolish and excavate dirt 1 LS 1,800.00 $1,800.00
from existing median. Install new curb
and gutter and 6" thick reinforced
median cap including subgrade
treatment. Shorten median by +1- 10
feet.
Total Revision to Contract Amount $3,200.00
Previous contract amount $ 778,000.00
Net increase in contract amount $ 3,200.00
Revised contract amount $ 781,200.00
Net increase in contract time of completion 0 Calendar Days
Revised Contract time of completion 150 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and
satisfaction of all past and future liability originating under any clause in the Contract by reason of this
revision to the Contract.
Reco . - - : - d y Engineer Date '
/ A _ -)7-10/
Agree t .y Con u .tor Date Acc - • by Owner Date