ST0202-CN031001 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Bethel School Road Project # ST 02-02 CONTRACTOR: Tiseo Paving Company OWNER: City of Coppell CHANGE ORDER NO.: ONE (1) DATE: October 1, 2003 Unit Item Description Quantity Unit Total Price ADD: New Block Sodding 335 SY 4.00 $1,340.00 Total Revision to Contract Amount $1,340.00 Previous contract amount $297,813.35 Net increase in contract amount $1,340.00 Revised contract amount $299,153.35 Net increase in contract time of completion -0- Revised Contract time of completion 75 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. ________________________________________ Recommended by City Engineer Date ________________________________________ Accepted by City Manager Date ____________________________________ Agreed to by Contractor Date