ST0202-CN031001
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Bethel School Road Project # ST 02-02
CONTRACTOR: Tiseo Paving Company
OWNER: City of Coppell
CHANGE ORDER NO.: ONE (1) DATE: October 1, 2003
Unit
Item Description Quantity Unit Total
Price
ADD: New Block Sodding 335 SY 4.00 $1,340.00
Total Revision to Contract Amount $1,340.00
Previous contract amount $297,813.35
Net increase in contract amount $1,340.00
Revised contract amount $299,153.35
Net increase in contract time of completion -0-
Revised Contract time of completion 75 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
________________________________________
Recommended by City Engineer Date
________________________________________
Accepted by City Manager Date
____________________________________
Agreed to by Contractor Date