SW0801-CN101222CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: SW08 -01 Denton Tap Infill
CONTRACTOR: 3D Paving and Contracting, L.L.C.
OWNER: City of Coppell
CHANGE ORDER NO.: 1 DATE: 12 -22 -2010
Item Description Quantity Unit Unit Price Total
ADD: 23 Grading & Sod at 1 LS $4,516.44 $4,516.44
120 S. Denton Tap
(Town Oaks Center)
DELETE: 13 Retaining Wall (225) SF $20.00 (4,500.00)
Total Revision to Contract Amount $16.44
Original contract amount $ 231,754.00
Net increase by previous authorized Change Orders $0.00
Revised Contract amount prior to this Change Order $231,754.00
Net increase in contract amount $ 16.44
Revised contract amount $ 231,770.44
Cumulative increase in TOTAL change order amount (Percentage) <1%
Net increase in contract time of completion 5 calendar days
Revised Contract time of completion 1 55 calendar days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
/ A� /- P..Zd 1 . 6. 11
R kornmended byl6ty Engineer Date
/ 7-
Agr ed to by CoITtractor Date
4 /' � Z
Accep d by City Date
3D Paring and Contracting, LLC
P.0, BOX 16982 1'OPPELL, TX. 750 OFFICE: 972- 393 -2876 AX- 97% -393 -1865
December 20, 2010
DENTON TAP SIDEWALK iNFILL
Supply equipment, material, and labor to complete the following scope of work:
Shape the landscape along 120 Denton lap at Town Oaks Center approx. 20OLF and install approx.
2,4005F of sod to match existing (Tiff 917):
SOD: S680.8S
Nate :Add 5 cal. Days to existing contract.
EQUIPMENT: $525.00
TRUCKING. $650.00
LABOR: $2,250.00
PROFIT & OVERHEAD: $410.59
TOTAL $4,516.
R r Dupre
nagfig PartOr
Page 1 of 1
George Marshall - SW08-01 Denton Tap Sidewalk
From: George Marshall
To: roger_3dcontracting@verizon.net
Date: 12/22/2010 9:19 AM
Subject: SW08-01 Denton Tap Sidewalk
Roger,
In regards to the change order presented to us for the grading work at 120 S. Denton Tap. I would like for you
to add a reduction in retaining wall quantity of 225 sf at $20/sf = $4500. This should still leave us with plenty of
retaining wall to complete the project.
If you could change your change order back to 1) a lump sum for grading & sod work and 2) a reduction in
retaining wall.
Thank You, George