ST0301A-CS100823 (2) Page 1 of 1 Keith Marvin - Bethel Rd - Wall Footing removal From:   "Dean Dumke" <deand@JRJPaving.com> To:   "Keith Marvin" <kmarvin@coppelltx.gov> Date:   8/23/2010 10:26 AM Subject:   Bethel Rd - Wall Footing removal   Keith,   Any word on if we are going to remove the 55’ of the north wall footing?  Besides paying for the 385 sf of footing poured, the impact of the removal is only $3,500 of the total change order impact addition.  I would like to get this resolved early this week so that it can be removed and backfilled so that it does not impact the paving operation that is working on starting tentatively next week.   Thank you,   Dean Dumke Sr Project Manager #469-223-7879 JRJ PAVING, L. P. _______________________       file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C724CE2City_...1/13/2011