Keith Marvin - Bethel Rd - Wall Footing removal
From: "Dean Dumke" <deand@JRJPaving.com>
To: "Keith Marvin" <kmarvin@coppelltx.gov>
Date: 8/23/2010 10:26 AM
Subject: Bethel Rd - Wall Footing removal
Keith,
Any word on if we are going to remove the 55’ of the north wall footing? Besides paying for the 385 sf of footing
poured, the impact of the removal is only $3,500 of the total change order impact addition. I would like to get this
resolved early this week so that it can be removed and backfilled so that it does not impact the paving operation
that is working on starting tentatively next week.
Thank you,
Dean Dumke
Sr Project Manager
#469-223-7879
JRJ PAVING, L. P.