ST0301A-CS1008302011) Keith Marvin - SS Aerial Crossing - Cantilever section Page 1
From:
Caleb Thornhill <bct @freese.com>
To:
Keith Marvin <kmarvin @coppelltx.gov>
Date:
8/30/2010 4:13 PM
Subject:
SS Aerial Crossing - Cantilever section
Attachments:
20100830160453. pdf
Keith,
Here is the closest detail we have to what you were describing. I haven't seen one with the steel detailed.
B. Caleb Thornhill P.E.
Project Manager
[cid: image001. jpg @01 CB485E.0885CO20]
Freese and Nichols, Inc. <http: / /www.freese.com />
* Main: 214 - 217 -2200
* Direct: 214- 217 -2282
* Fax: 214 - 920 -2565
* Email: bct@freese. com < mai Ito bct@freese. com >
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed.
This message, together with any attachment, may contain the sender's organization's confidential and
privileged information. The recipient is hereby notified to treat the information as confidential and
privileged and to not disclose or use the information except as authorized by sender's organization. Any
unauthorized review, printing, retention, copying, disclosure, distribution, retransmission, dissemination or
other use of, or taking of any action in reliance upon, this information by persons or entities other than the
intended recipient is prohibited. If you received this message in error, please immediately contact the
sender by reply email and delete all copies of the material from any computer. Thank you for your
cooperation.
z _ .$
0
N Z u a°S
a = °a
U -
o
z -cW� °-
�n
00
t 8 0
Z ^iin
y'ver
LLC &a.
XISTING
3RIDGE
3 - 0"
(FIELD VERIFY)
12" MIN
FROM EDGE
4 -5/8 "0 A.B. HILT] QUICKBOLT TZ
/- CONCRETE ATTACHMENT PLATE
GRINNELL, FIG 52 FOR 1 "0 ROD
"0 ROD HANGER BY GRINNELL
ADJUSTABLE CLEVIS HANGER AS
MANUFACTURED BY GRINNELL,
FIG 260 FOR 16 "0 PIPE
16 "0
PIPE
TYPE C GIRDER (EXISTING)
n PIPE SUPPORT @ 10' C/C MAX.
PL -2 DT -1 NOT TO SCALE
Z
W
M
W
U
Q
J �
� J
W
a <
x W W
Z C)
J
o J <
Q S LL
U O
W
o
Q �
U)
U W
Q
O
ry n
fr
W
t
7
m
U
N
T
a
I
< a
=a
Wm
—c
00
ovd
Cd°
OG�
Q
U
} I(1
LL
W 6
>O
SHEET
DT -1
75% SUBMITTAL I SM.
5
2011) Keith Marvin - RE: Bethel Road, Page 1
From: Caleb Thornhill <bct @freese.com>
To: Keith Marvin <kmarvin @coppelltx.gov >, Chris Poteet <cjp @freese.com>
CC: Tricia Hatley <thh @freese.com>
Date: 8/30/2010 10:16 AM
Subject: RE: Bethel Road,
Keith,
have not heard a response
On a separate issue, Chris and Winston said you were asking about a Pier and Cap cantilever detail for
the SS aerial crossing. We do not have a cantilever detail, but we do have a standard Pier and Cap detail
Would you like me to send this over?
I'm going to set up a meeting with Rick to review the South Coppell record drawings before our meeting
Friday. I'll let you know when it's coordinated in case you would like to stop by.
B. Caleb Thornhill, P.E.
Freese & Nichols, Inc.
214 - 217 -2282
- - - -- Original Message---- -
From: Keith Marvin [mailto:kmarvin @coppelltx.gov]
Sent: Monday, August 30, 2010 10:01 AM
To: Caleb Thornhill; Chris Poteet
Cc: Tricia Hatley
Subject: RE: Bethel Road,
Have we got a response for the contractor on this submittal yet?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304 -3681
>>> Chris Poteet <cjp @freese.com> 8/19/2010 2:01 PM >>>
Keith, not a problem. I'm going through it now.
Chris
Chris Poteet
Freese & Nichols Inc.
- - - -- Original Message---- -
From: Keith Marvin [mailto:kmarvin @coppelltx.gov]
Sent: Thursday, August 19, 2010 1:57 PM
To: Chris Poteet
Cc: Tricia Hatley
Subject: Fwd: Bethel Road,
Chris,
understand Caleb is out this week. Can you and the structural engineer review the attached submittal.
This is for cement treated base backfill for the bridge.
2011) Keith Marvin - RE: Bethel Road, Page 2
Thanks.
Keith Marvin, P.E.
Project Engineer
(972) 304 -3681
>>> "Kim Entrekin" <Kime @JRJ Paving. com> 8/19/2010 12:06 PM >>>
Hard copies are being sent via Fed Ex, the tracking number is 8735 6673 2320. Keith you should receive
them tomorrow morning. Please do not hesitate to contact me if they do not arrive.
Kim Entrekin
JRJ Paving, LP
214 - 466 -8340
214 - 466- 8354(fax)
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed.
This message, together with any attachment, may contain the sender's organization's confidential and
privileged information. The recipient is hereby notified to treat the information as confidential and
privileged and to not disclose or use the information except as authorized by sender's organization. Any
unauthorized review, printing, retention, copying, disclosure, distribution, retransmission, dissemination or
other use of, or taking of any action in reliance upon, this information by persons or entities other than the
intended recipient is prohibited. If you received this message in error, please immediately contact the
sender by reply email and delete all copies of the material from any computer. Thank you for your
cooperation.
Page 1 of 1
Keith Marvin - Bethel Rd - N Wall Removal
From: "Dean Dumke" <deand(�JRJPaving.com>
To: "Keith Marvin" <kmarvin(�'.&oppelltx.gov>
Date: 8/30/2010 4:03 PM
Subject: Bethel Rd - N Wall Removal
Attachments: CO 11 R Remove N Wall Footing.pdf
Keith,
need to know if the attached change order has been approved to remove the existing wall off of Luis's property.
If so, I will also need a revised set of plans showing the new location of the wall so I can get it staked and
reinstalled in the correct location. We are trying to get the steel ordered and move forward on the wall repairs.
The goal is to get the entire north wall poured by the end of next week, but to accomplishing this, I need this last
62' resolved so that we can get this area removed and the necessary steel ordered, installed, and footing poured
back.
Please advise as to where we are pertaining to this specific location.
Thank you,
Dean Dumke
Sr Project Manager
#469- 223 -7879
JRJ PAVING, L. P.
file: HC: \Documents and Settings \radloo \Local Setting s\Temp\XPgrpwi se\4 C 7B D 660 City_... 1/13/2011
JRJ PAVING, L.P.
Proposed Change Order IIR
DATE: 8/24/2010
TO: City of CoppelI PROPOSAL FOR : Bethel Rd II
ATTN: Keith Marvin
Item Description Unit Quantity Unit Price
1 Remove Concrete Footing Installed (62' of Wall at 7' Average) SF 434 $20.40
2 Excavate & Remove Concrete Footing (62' of Wall at T average) Day 1 $1,860.00
3 Haul Concrete to Big City LD 4 $180.00
4 Cost for Reinforcing Wall Steel (On Site and not Used) LBS 2142 $0.78
Total if wall not rebuilt, Items 1 -4
Total if wall is rebuilt in new location, Items 1 -3, with item 206 on contract used to build back wall
Item 1 listed pricing is 50% of unit price of contract item 206.
Item 4 will be deleted if the the wall is reinstalled
Should you have any questions or require additional information please feel free to call me.
Respectfully Submitted,
Total Amount
$8,853.60
$1,860.00
$720.00
$1,670.76
$13,104.36
$11,433.60
Dean Dumke
Sr Project Manager