Keith Marvin - RE: Bethel Road Reconstruction - Retrofit footing and wall details
From: Caleb Thornhill <bct@freese.com>
To: Dean Dumke <deand@JRJPaving.com>, Keith Marvin <kmarvin@coppelltx.gov>
Date: 8/30/2010 8:57 AM
Subject: RE: Bethel Road Reconstruction - Retrofit footing and wall details
CC: CPL03243 <CPL03243@freese.com>, Peter Kau <vbk@freese.com>
Dean,
I did talk to Peter about cutting the existing steel. He said it is acceptable to leave the existing steel in place, as
long as the proper steel placement is installed for the wall and the footing and the existing steel is within the
new wall stem.
Let me know if you have any questions.
B. Caleb Thornhill, P.E.
Freese & Nichols, Inc.
214-217-2282
From: Dean Dumke [mailto:deand@JRJPaving.com]
Sent: Monday, August 30, 2010 8:55 AM
To: Caleb Thornhill
Subject: RE: Bethel Road Reconstruction - Retrofit footing and wall details
Nope.
Our server went down on Friday at 2pm and they did not get it fixed until sometime this weekend. I see you sent
it, but I never got this detail.
Thanks for resending,
Dean Dumke
Sr Project Manager
#469-223-7879
JRJ PAVING, L. P.
_______________________
From: Caleb Thornhill [mailto:bct@freese.com]
Sent: Monday, August 30, 2010 8:48 AM
To: Dean Dumke; steve@ntbridge.com; Keith Marvin
Cc: CPL03243
Subject: FW: Bethel Road Reconstruction - Retrofit footing and wall details
Dean,
I sent this over Friday. Are you referring to something else?
B. Caleb Thornhill, P.E.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C7B728BCity_...1/25/2011
Page 2 of 2
Freese & Nichols, Inc.
214-217-2282
From: Caleb Thornhill
Sent: Friday, August 27, 2010 3:49 PM
To: 'steve@ntbridge.com'; 'Dean Dumke'; 'Keith Marvin'
Cc: Tricia Hatley; Chris Poteet; Winston Silvia; 'cpl03243@freese.com'; Peter Kau
Subject: Bethel Road Reconstruction - Retrofit footing and wall details
Keith/Dean,
Attached is the completed signed sealed detail to retrofit the existing footing and wall constructed in the field.
Keith, I will send over 5 full and 3 half size hard copies Monday.
We will send a detailed retaining wall layout by next Tuesday to complete both the north and south retaining
walls.
Call me with any questions you might have.
B. Caleb Thornhill P.E.
Project Manager
Freese and Nichols, Inc.
Main: 214-217-2200
Direct: 214-217-2282
Fax: 214-920-2565
Email: bct@freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C7B728BCity_...1/25/2011
Page 1 of 1
Keith Marvin - RE: Bethel Road Reconstruction - New footing placement
From: "Dean Dumke" <deand@JRJPaving.com>
To: "Caleb Thornhill" <bct@freese.com>, <steve@ntbridge.com>
Date: 8/30/2010 4:33 PM
Subject: RE: Bethel Road Reconstruction - New footing placement
CC:"Keith Marvin" <kmarvin@coppelltx.gov>, "CPL03243" <CPL03243@freese.com>, "Peter Kau"
<vbk@freese.com>, "Chris Poteet" <cjp@freese.com>, "Winston Silvia" <was@freese.com>
Gentlemen:
North Texas Bridge is in the process of ordering steel to make the necessary corrections. I am hoping, by Wednesday, to
know when the first section on the north side will be ready for inspection with the first pour either Thursday or Friday this
week.
Thank you,
Dean Dumke
Sr Project Manager
#469-223-7879
JRJ PAVING, L. P.
_______________________
From: Caleb Thornhill [mailto:bct@freese.com]
Sent: Monday, August 30, 2010 3:46 PM
To: Dean Dumke
Cc: Keith Marvin; CPL03243; Peter Kau; Chris Poteet; Winston Silvia
Subject: Bethel Road Reconstruction - New footing placement
Dean,
Please let me know when you guys start setting the rebar for the new footing. We’d like to come out and inspect the
placement.
B. Caleb Thornhill P.E.
Project Manager
Freese and Nichols, Inc.
Main: 214-217-2200
Direct: 214-217-2282
Fax: 214-920-2565
Email: bct@freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment, may contain
the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential and privileged and to not
disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention, copying, disclosure, distribution,
retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the intended recipient is
prohibited. If you received this message in error, please immediately contact the sender by reply email and delete all copies of the material from any computer.
Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C7BDD74City...1/13/2011