Loading...
ST0301A-CS100909 Page 1 of 2 Keith Marvin - Re:  Bethel Road Reconstruction - Approved Submittal for Cement        Treated Base Backfill From:   <steve@ntbridge.com> To: "Caleb Thornhill" <bct@freese.com>, <steve@ntbridge.com>, "Keith Marvin"     <kmarvin@coppelltx.gov>, "Dean Dumke"    <deand@JRJPaving.com> Date:    9/9/2010 5:46 PM Subject:Re:  Bethel Road Reconstruction - Approved Submittal for Cement        Treated Base     Backfill CC: "CPL03243" <CPL03243@freese.com>, "Peter Kau" <vbk@freese.com>, "Chris Poteet"     <cjp@freese.com> Attachments:    image001.jpg   Caleb When will you know if a screen wall is added? We should be ready for a rebar inspection on Monday afternoon and place concrete on Tuesday, so we need to know about the added screen wall by Monday at Noon   Thanks   Steve Goodman -----Original Message----- From: Caleb Thornhill [mailto:bct@freese.com] Sent: Thursday, September 9, 2010 05:35 PM To: steve@ntbridge.com, 'Keith Marvin', 'Dean Dumke' Cc: 'CPL03243', 'Peter Kau', 'Chris Poteet' Subject: RE: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill Steve,    The vert bar shown at 5? C-C is in case the screening wall is being added.  If we only put a traffic rail on          the wall, these can be removed.  Structures is verifying the need for select backfill.  I will have a response to you in the morning.           Natural ground is acceptable for the 1ft space beyond the concrete placement           0?, flush, is acceptable            B. Caleb Thornhill, P.E. Freese & Nichols, Inc. 214-217-2282 From: steve@ntbridge.com [mailto:steve@ntbridge.com] Sent: Thursday, September 09, 2010 9:25 AM To: Caleb Thornhill Subject: Re: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill   I had questions on your wall modification detail that have not been answered:   There is a vert bar shown at 5" ctrs that should be 15"? See the upper Left Detail There is select backfill shown with no pay item?  There is a 1 Ft space beyond the concrete placement that shows select fill? I would propose the concrete to be placed against natural ground maybe (12" min) maybe 15-16" from the exist footing.  RW2 shows a keyway with a 2x4 placed at the top of the wall footing? It says 0-2" in Ht. We will place the 2x4 at 0", flush file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C891D84City_...1/13/2011 Page 2 of 2 with the top of the footing. RW2   We have the reinforcing on site and will begin the modifications Monday September 13   Please clarify so we have no questions on the site   Thanks   Steve Goodman NTBC -----Original Message----- From: Caleb Thornhill [mailto:bct@freese.com] Sent: Wednesday, September 8, 2010 05:50 PM To: 'Keith Marvin', 'Dean Dumke' Cc: steve@ntbridge.com, 'CPL03243', 'Chris Poteet', 'Tony Diaz' Subject: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill Keith/Dean,   Cement Treated Base Backfill has been approved.  See attached for your reference.   B. Caleb Thornhill P.E. Project Manager FNI%20Logo%20-%20Blue%20-%20RGB.jpg Freese and Nichols, Inc. Main: 214-217-2200  Direct: 214-217-2282  Fax: 214-920-2565  Email: bct@freese.com    Please consider the environment before printing this message. This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment, may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention, copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and delete all copies of the material from any computer. Thank you for your cooperation.   file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C891D84City_...1/13/2011 (1/13/2011) Keith Marvin - FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base BackfillPage 1 From: "Dean Dumke" <deand@JRJPaving.com> To: "Keith Marvin" <kmarvin@coppelltx.gov> Date: 9/9/2010 3:36 PM Subject: FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill Attachments: image001.jpg Keith, Just saw this email sent to Caleb from Steve, N TX Bridge. Can I get you to push to get these items answered by tomorrow so that we do not have any further hiccups. If select fill is required, we will have to have an additional pay item. I think they were wanting the same natural material we were using before, but that is not what detail shows. Thanks, Dean Dumke Sr Project Manager #469-223-7879 JRJ PAVING, L. P. _______________________ ________________________________ From: steve@ntbridge.com [mailto:steve@ntbridge.com] Sent: Thursday, September 09, 2010 11:24 AM To: Dean Dumke Subject: Fwd: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill -----Original Message----- From: steve@ntbridge.com [mailto:steve@ntbridge.com] Sent: Thursday, September 9, 2010 10:24 AM To: 'Caleb Thornhill' Subject: Re: Bethel Road Reconstruction - Approved Submittal for Cement (1/13/2011) Keith Marvin - FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base BackfillPage 2 Treated Base Backfill I had questions on your wall modification detail that have not been answered: There is a vert bar shown at 5" ctrs that should be 15"? See the upper Left Detail There is select backfill shown with no pay item? There is a 1 Ft space beyond the concrete placement that shows select fill? I would propose the concrete to be placed against natural ground maybe (12" min) maybe 15-16" from the exist footing. RW2 shows a keyway with a 2x4 placed at the top of the wall footing? It says 0-2" in Ht. We will place the 2x4 at 0", flush with the top of the footing. RW2 We have the reinforcing on site and will begin the modifications Monday September 13 Please clarify so we have no questions on the site Thanks Steve Goodman NTBC -----Original Message----- From: Caleb Thornhill [mailto:bct@freese.com] Sent: Wednesday, September 8, 2010 05:50 PM To: 'Keith Marvin', 'Dean Dumke' Cc: steve@ntbridge.com, 'CPL03243', 'Chris Poteet', 'Tony Diaz' Subject: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill Keith/Dean, Cement Treated Base Backfill has been approved. See attached for your reference. (1/13/2011) Keith Marvin - FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base BackfillPage 3 B. Caleb Thornhill P.E. Project Manager Freese and Nichols, Inc. <http://www.freese.com/> * Main: 214-217-2200 * Direct: 214-217-2282 * Fax: 214-920-2565 * Email: bct@freese.com Please consider the environment before printing this message. ________________________________ This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment, may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention, copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and delete all copies of the material from any computer. Thank you for your cooperation.