ST0301A-CS100909
Page 1 of 2
Keith Marvin - Re: Bethel Road Reconstruction - Approved Submittal for Cement Treated
Base Backfill
From: <steve@ntbridge.com>
To:
"Caleb Thornhill" <bct@freese.com>, <steve@ntbridge.com>, "Keith Marvin"
<kmarvin@coppelltx.gov>, "Dean Dumke" <deand@JRJPaving.com>
Date:
9/9/2010 5:46 PM
Subject:Re: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base
Backfill
CC:
"CPL03243" <CPL03243@freese.com>, "Peter Kau" <vbk@freese.com>, "Chris Poteet"
<cjp@freese.com>
Attachments:
image001.jpg
Caleb
When will you know if a screen wall is added?
We should be ready for a rebar inspection on Monday afternoon and place concrete on Tuesday, so we need to know about the
added screen wall by Monday at Noon
Thanks
Steve Goodman
-----Original Message-----
From: Caleb Thornhill [mailto:bct@freese.com]
Sent: Thursday, September 9, 2010 05:35 PM
To: steve@ntbridge.com, 'Keith Marvin', 'Dean Dumke'
Cc: 'CPL03243', 'Peter Kau', 'Chris Poteet'
Subject: RE: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill
Steve,
The vert bar shown at 5? C-C is in case the screening wall is being added. If we only put a traffic rail on
the wall, these can be removed.
Structures is verifying the need for select backfill. I will have a response to you in the morning.
Natural ground is acceptable for the 1ft space beyond the concrete placement
0?, flush, is acceptable
B. Caleb Thornhill, P.E.
Freese & Nichols, Inc.
214-217-2282
From: steve@ntbridge.com [mailto:steve@ntbridge.com]
Sent: Thursday, September 09, 2010 9:25 AM
To: Caleb Thornhill
Subject: Re: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill
I had questions on your wall modification detail that have not been answered:
There is a vert bar shown at 5" ctrs that should be 15"? See the upper Left Detail
There is select backfill shown with no pay item?
There is a 1 Ft space beyond the concrete placement that shows select fill? I would propose the concrete to be placed against
natural ground maybe (12" min) maybe 15-16" from the exist footing.
RW2 shows a keyway with a 2x4 placed at the top of the wall footing? It says 0-2" in Ht. We will place the 2x4 at 0", flush
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C891D84City_...1/13/2011
Page 2 of 2
with the top of the footing. RW2
We have the reinforcing on site and will begin the modifications Monday September 13
Please clarify so we have no questions on the site
Thanks
Steve Goodman
NTBC
-----Original Message-----
From: Caleb Thornhill [mailto:bct@freese.com]
Sent: Wednesday, September 8, 2010 05:50 PM
To: 'Keith Marvin', 'Dean Dumke'
Cc: steve@ntbridge.com, 'CPL03243', 'Chris Poteet', 'Tony Diaz'
Subject: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill
Keith/Dean,
Cement Treated Base Backfill has been approved. See attached for your reference.
B. Caleb Thornhill P.E.
Project Manager
FNI%20Logo%20-%20Blue%20-%20RGB.jpg
Freese and Nichols, Inc.
Main: 214-217-2200
Direct: 214-217-2282
Fax: 214-920-2565
Email: bct@freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C891D84City_...1/13/2011
(1/13/2011) Keith Marvin - FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base BackfillPage 1
From:
"Dean Dumke" <deand@JRJPaving.com>
To:
"Keith Marvin" <kmarvin@coppelltx.gov>
Date:
9/9/2010 3:36 PM
Subject:
FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base
Backfill
Attachments:
image001.jpg
Keith,
Just saw this email sent to Caleb from Steve, N TX Bridge. Can I get
you to push to get these items answered by tomorrow so that we do not
have any further hiccups. If select fill is required, we will have to
have an additional pay item. I think they were wanting the same natural
material we were using before, but that is not what detail shows.
Thanks,
Dean Dumke
Sr Project Manager
#469-223-7879
JRJ PAVING, L. P.
_______________________
________________________________
From: steve@ntbridge.com [mailto:steve@ntbridge.com]
Sent: Thursday, September 09, 2010 11:24 AM
To: Dean Dumke
Subject: Fwd: Bethel Road Reconstruction - Approved Submittal for Cement
Treated Base Backfill
-----Original Message-----
From: steve@ntbridge.com [mailto:steve@ntbridge.com]
Sent: Thursday, September 9, 2010 10:24 AM
To: 'Caleb Thornhill'
Subject: Re: Bethel Road Reconstruction - Approved Submittal for Cement
(1/13/2011) Keith Marvin - FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base BackfillPage 2
Treated Base Backfill
I had questions on your wall modification detail that have not been
answered:
There is a vert bar shown at 5" ctrs that should be 15"? See the upper
Left Detail
There is select backfill shown with no pay item?
There is a 1 Ft space beyond the concrete placement that shows select
fill? I would propose the concrete to be placed against natural ground
maybe (12" min) maybe 15-16" from the exist footing.
RW2 shows a keyway with a 2x4 placed at the top of the wall footing? It
says 0-2" in Ht. We will place the 2x4 at 0", flush with the top of the
footing. RW2
We have the reinforcing on site and will begin the modifications Monday
September 13
Please clarify so we have no questions on the site
Thanks
Steve Goodman
NTBC
-----Original Message-----
From: Caleb Thornhill [mailto:bct@freese.com]
Sent: Wednesday, September 8, 2010 05:50 PM
To: 'Keith Marvin', 'Dean Dumke'
Cc: steve@ntbridge.com, 'CPL03243', 'Chris Poteet', 'Tony Diaz'
Subject: Bethel Road Reconstruction - Approved Submittal for Cement
Treated Base Backfill
Keith/Dean,
Cement Treated Base Backfill has been approved. See attached for your
reference.
(1/13/2011) Keith Marvin - FW: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base BackfillPage 3
B. Caleb Thornhill P.E.
Project Manager
Freese and Nichols, Inc. <http://www.freese.com/>
* Main: 214-217-2200
* Direct: 214-217-2282
* Fax: 214-920-2565
* Email: bct@freese.com
Please consider the environment before printing this message.
________________________________
This electronic mail message is intended exclusively for the individual
or entity to which it is addressed. This message, together with any
attachment, may contain the sender's organization's confidential and
privileged information. The recipient is hereby notified to treat the
information as confidential and privileged and to not disclose or use
the information except as authorized by sender's organization. Any
unauthorized review, printing, retention, copying, disclosure,
distribution, retransmission, dissemination or other use of, or taking
of any action in reliance upon, this information by persons or entities
other than the intended recipient is prohibited. If you received this
message in error, please immediately contact the sender by reply email
and delete all copies of the material from any computer. Thank you for
your cooperation.