ST0301A-CN100917
Page 1 of 2
Keith Marvin - Re: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base
Backfill
From: <steve@ntbridge.com>
To:
"Caleb Thornhill" <bct@freese.com>, "Keith Marvin" <kmarvin@coppelltx.gov>,
"Dean Dumke" <deand@JRJPaving.com>
Date:
9/27/2010 1:19 PM
Subject:Re: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base
Backfill
CC:
<steve@ntbridge.com>, "CPL03243" <CPL03243@freese.com>, "Chris Poteet"
<cjp@freese.com>, "Tony Diaz" <AD@freese.com>
Attachments:
image001.jpg
----RFI # 16 BRIDGE RAIL HT
I have a question on the Br Rail Ht shown as 4'-6" in the plans---The Coppell Rail is 3'-6" and thats what we are
installing on the retaining walls
All the bridges in Coppell now have the Coppell Rail and are all 3'-6" tall to match what we will have on the
retaining walls
3'-6" appears to be the correct HT for the bridge rail not 4'-6"
PLEASE CONFIRM!!
Steve Goodman
NTBC
-Original Message-----
From: Caleb Thornhill [mailto:bct@freese.com]
Sent: Wednesday, September 8, 2010 05:50 PM
To: 'Keith Marvin', 'Dean Dumke'
Cc: steve@ntbridge.com, 'CPL03243', 'Chris Poteet', 'Tony Diaz'
Subject: Bethel Road Reconstruction - Approved Submittal for Cement Treated Base Backfill
Keith/Dean,
Cement Treated Base Backfill has been approved. See attached for your reference.
B. Caleb Thornhill P.E.
Project Manager
FNI%20Logo%20-%20Blue%20-%20RGB.jpg
Freese and Nichols, Inc.
Main: 214-217-2200
Direct: 214-217-2282
Fax: 214-920-2565
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4CA099DECity_...1/14/2011
Page 2 of 2
Email: bct@freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4CA099DECity_...1/14/2011
JRJ PAVING, L. P.
_______________________
1805 Royal Lane, Suite 107
Dallas, Texas 75229
214-466-8340 Phone
214-466-8354 Fax
REQUEST FOR INFORMATION
Project:Bethel Road
RFI No:16
Date:September 17, 2010
Subject:North Retaining Wall - Coppell Rail Section
Reference Drawing:GR-1
INFORMATION REQUESTED:
1.Per our discussion yesterday, the last 30' of the North Retaining Wall is to be solid instead of
"Coppell Rail", the remaining 270' of wall is to have the "Coppell Rail" installed per plan.
Please provide me with confirmation that this is correct so that we build and final out this
multiple changed wall area.
Requested by:
Dean Dumke
Sr Project Manager
deand@jrjpaving.com