ST0301A-CN110110CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Bethel Road H (ST 03 -01A)
CONTRACTOR: JRJ Paving, L.P.
OWNER: City of Coppell
CHANGE ORDER NO.: Four (4) DATE: January 10, 2011 Pagel of 2
1. Bank stabilization at northeast corner of bridge. This work is necessary to protect private
infrastructure adjacent to our work. Gabion work is in lieu of concrete rip -rap as originally
designed.
2. Cost to add one set of pedestrian push buttons and signals at Bethel & Denton Tap.
3. Cost reduction associated with city supplying new traffic signal controller cabinet.
4. Cost reduction associated with changing the type and location of guardrails.
Item Description
ADD: 1.
Gabion bank
stabilization
2.
PED Signal Section
3.
PED pushbutton &
2 EA
sign assembly
Total Additions:
DEDUCT: 200.
Reduction of rip -rap
quantity in location
of Gabion
installation.
1.
Cost reduction for
city supplying
controller cabinet
2.
Cost reduction for
Guardrail changes
Total Deductions:
Quantity Unit Unit Price Total
1 LS
$43,065.00
$43,065.00
2 EA
$585.00
$1,170.00
2 EA
$130.00
$260.00
$44,495.00
42 CY $214.20 ($8,996.40)
1 LS $7,875.00 ($7,875.00)
1 LS $7,803.30 ($7,803.30)
($24,674.70)
Net Change:
$19,820.30
Previous contract amount
Net increase m contract amount Change Order # 1
(8 -3 -2010)
Net increase in contract amount Change Order #2
(8 -10 -2010 council approved)
Net increase in contract amount Change Order #3
(10 -28 -2010)
Net increase in contract amount Change Order #4
Revised contract amount
Cumulative increase in TOTAL change order amount (Percentage)
Net increase in contract time of completion
Revised Contract time of c ompletion
$1,969,019.50
$23,505.50
$98,431.33
$16,215.00
$19,820.30
$ 2,126,991.63
8.0%
0
270 Calendar Days
The contractor hereby accepts this Contract adjustment as a fmal and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
by CK Engineer Date
Agreed to &Contractor 'Date
Z�� � �I� j) 2-tj�l ,
Accepted by Vity Date