I know. Thanks
>>> Keith Marvin 8/20/2010 4:19 PM >>>
It should be no more than the $98,431.33.
Keith
>>> Chad Beach 8/20/2010 4:15 PM >>>
I got it, I will amend Glenn's Utility Ops budget, 02-03-17-5220 for the $100,000.
>>> Keith Marvin 8/20/2010 12:14 PM >>>
We took a change order to council last meeting for this sewer line. I'll get you a copy of it.
Keith
-----Original Message-----
From: Chad Beach
Cc: Glenn Hollowell <GHOLLOW@coppelltx.gov>
To: Keith Marvin <KMARVIN@coppelltx.gov>
Sent: 8/20/2010 10:45:22 AM
Subject: Sewer Line - Bethel Rd Project
Keith, a few weeks ago Glenn and Ken ask me about funding for a sewer line related to the Bethel Rd project now under
construction. I told Glenn the funding for the sewer line would be charged to 02-03-17-5220 and Finance would include that
amount in the budget amendment we are taking to council during Sept. Ken and Glenn mentioned the cost would be approx
$100,000. Please provide me with a good estimate and confirm these funds are still needed.