(1/28/2011) Keith Marvin - FW: Change order number 3 - Bethel Road Part 2Page 1
From:
"Dean Dumke" <deand@JRJPaving.com>
To:
"Keith Marvin" <kmarvin@coppelltx.gov>
Date:
10/13/2010 3:57 PM
Subject:
FW: Change order number 3 - Bethel Road Part 2
Keith,
I forgot about the $507.06 check we wrote for ONCOR to hold up the pole.
That was the 2nd check JRJ wrote. I was reviewing my change order
summary and realized I left this one off.
Dean
-----Original Message-----
From: Dean Dumke
Sent: Wednesday, October 13, 2010 3:25 PM
To: 'Keith Marvin'
Subject: RE: Change order number 3 - Bethel Road
Keith,
I have reviewed what you sent and at this time everything is accounted
for except one item listed on the drain at the spring change order:
4"PVC Pipe outfall through curb w/ 2- 2" Pipe15 lf at $2.40/lf =
$36.00.
The French drain was omitted, but the other was necessary and Larry
wanted it installed. If you can get this back to me, I can get signed
for full execution of the change order.
Thanks,
Dean Dumke
Sr Project Manager
JRJ Paving
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Wednesday, October 13, 2010 8:43 AM
To: Dean Dumke
Cc: Kim Entrekin; Marty Murphy
Subject: Change order number 3 - Bethel Road
Dean,
Please review what I have on change order number 3. These are all the
outstanding items I am aware of. Please let me know if I've forgotten
anything.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
(1/28/2011) Keith Marvin - RE: Change order number 3 - Bethel RoadPage 1
From:
"Dean Dumke" <deand@JRJPaving.com>
To:
"Keith Marvin" <kmarvin@coppelltx.gov>
Date:
10/13/2010 3:23 PM
Subject:
RE: Change order number 3 - Bethel Road
Keith,
I have reviewed what you sent and at this time everything is accounted
for except one item listed on the drain at the spring change order:
4"PVC Pipe outfall through curb w/ 2- 2" Pipe15 lf at $2.40/lf =
$36.00.
The French drain was omitted, but the other was necessary and Larry
wanted it installed. If you can get this back to me, I can get signed
for full execution of the change order.
Thanks,
Dean Dumke
Sr Project Manager
JRJ Paving
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Wednesday, October 13, 2010 8:43 AM
To: Dean Dumke
Cc: Kim Entrekin; Marty Murphy
Subject: Change order number 3 - Bethel Road
Dean,
Please review what I have on change order number 3. These are all the
outstanding items I am aware of. Please let me know if I've forgotten
anything.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681