Loading...
ST0301A-CR101104 (2) Page 1 of 1 Keith Marvin - Bethel Road Reconstruction - Site Visit Report From:   Caleb Thornhill <bct@freese.com> To:   Keith Marvin <kmarvin@coppelltx.gov> Date:   11/4/2010 3:24 PM Subject:   Bethel Road Reconstruction - Site Visit Report CC:   CPL03243 <CPL03243@freese.com>, Chris Poteet <cjp@freese.com> Attachments:   Site Visit Report 11-4-10.docx   Keith,   As we discussed on the phone, attached is the site visit report from today’s observations.  If you have any questions, feel free to call me.     B. Caleb Thornhill P.E. Project Manager Freese and Nichols, Inc. Main: 214-217-2200  Direct: 214-217-2282  Fax: 214-920-2565  Email: bct@freese.com    Please consider the environment before printing this message. This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment, may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention, copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and delete all copies of the material from any computer. Thank you for your cooperation. file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4CD2D013City_...1/28/2011 SITE VISIT MEMORANDUM OWNER: City of Coppell PROJECT NO.: CPL03243 PROJECT DESCRIPTION: Bethel Road DATE: 11-4-10 Reconstruction CONTRACTOR: JRJ Paving ARRIVAL TIME: 9:00 am RESIDENT REPRESENTATIVE: N/A DEPARTURE TIME: 11:00 am PERSON VISITING THIS SITE: B. Caleb Thornhill CONSTRUCTION ACTIVITIES OBSERVED: Road closed at Bridge. Bridge:  Deck is poured.  Contractor is beginning to set rebar and pour sections of bridge railing Road:  Half of roadway not completed from approx. STA 39+00 to 42+00 on South side of road. Area being graded. All remaining roadway appears to be complete. PHOTOGRAPHS TAKEN: YES NO ATTACHED FILED DISCUSSION WITH CONTRACTOR OR CITY INPSECTOR: Bridge/ Rip Rap placement on North/East side of Bridge  FNI reviewed the rip rap placement in this area. Tony Diaz (FNI) and Chuck Easton (FNI) are going to sketch up a plan to stabilize this area to prevent erosion and stabilize existing screening wall.  FNI noticed some erosion under the rip rap at the top of the slope. Tony and Chuck expressed concern about pockets behind the rip rap. Larry Davis (Coppell) said he is discussing with the contractor to fill this area with flowable fill to ensure the stability of the rip rap. Guardrail Placement  Larry Davis said he had concerns with the guardrail shown on the plans at the end of the of the bridge rail on the south/east side of the bridge. Grading Behind South Retaining Wall  Caleb Thornhill and Larry Davis discussed the grading between the retaining wall and the screening wall. Contractor has expressed concern about existing vegetation and access to this area. Larry said he would get with contractor to discuss. FOLLOW UP ACTION REQUIRED:  FNI will draft plan to stabilize bank and existing screening wall on NE side of Bridge. We will submit to the city for discussion purposes. REPORT SUBMITTED BY: B. Caleb Thornhill DATE: 11-4-10 ROUTING: BCT PM RES. REP.