Keith Marvin - RE: BETHEL AND DENTON-TAP SIGNALS
From: Per Birdsall
To: Dean Dumke; Johnny Heine
Date:11/10/2010 9:29 AM
Subject:RE: BETHEL AND DENTON-TAP SIGNALS
CC: Brent Adams; Brian Johnson; Keith Marvin; Mark Obar
All is a go for tomorrow at 9. I'll follow up to help insure attendance by our PD. Traffic control will also be
supplementing the "STOP" signs with stop ahead signs and coning the lane division lines on approach to the
intersection on Denton Tap Rd. Brent Adams will be coordinating those efforts for the City and will handle the
maintenance/temporary disruption of network communications that will be required during the cabinet
exchange.
Thank you all for your cooperation in planning for a smooth project. Per
Per Birdsall, Traffic Control / Streets Operations Manager
City of Coppell
816 S. Coppell Rd.
P.O. Box 9478
Coppell, Texas 75019
972-462-5150
972-462-5199 fax
pbirdsall@coppelltx.gov
Please note the NEW! email address.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4CDA65FACity...1/28/2011
Page 1 of 2
Keith Marvin - RE: BETHEL AND DENTON-TAP SIGNALS
From: "Dean Dumke" <deand@JRJPaving.com>
To: "Johnny Heine" <johnny@melselectric.com>, "Per Birdsall" <pbirdsall@coppelltx.gov>
Date: 11/10/2010 9:12 AM
Subject: RE: BETHEL AND DENTON-TAP SIGNALS
CC: "Mark Obar" <mark@melselectric.com>, "Keith Marvin" <kmarvin@coppelltx.gov>
I have spoken with Keith Marvin and he has requested that the lights be changed from regular operation to
flashing red for 30 minutes prior to turning off and having intersection controlled only by stop signs. Stop signs
are to be delivered today and laid down so that tomorrow at 9am they just have to be stood up until work has
been completed. Will and can all work that needs to be performed in the intersection be completed tomorrow
during the 2 scheduled brief interruptions?
Let me know ,
Dean Dumke
From: Johnny Heine [mailto:johnny@melselectric.com]
Sent: Wednesday, November 10, 2010 8:09 AM
To: Per Birdsall
Cc: Mark Obar; Dean Dumke
Subject: RE: BETHEL AND DENTON-TAP SIGNALS
Everything is still on for tomorrow correct?
From: Per Birdsall [mailto:pbirdsall@coppelltx.gov]
Sent: Monday, November 08, 2010 7:37 AM
To: Johnny Heine
Subject: RE: BETHEL AND DENTON-TAP SIGNALS
I spoke with the engineer. Sounds like a go. Only topic of discussion was wether PD should be there. I said it
would be preferable. Per
So far no objections to the plan. We will need to make interruptions to the City's network connection as brief as
possible. It will involve two brief interruptions. We will disconnect the switch and loop the patch cable back to
the trunk. At this point you can do what you need to do with the cabinet because the network will be patched
through. After the new cabinet is in place and running we can reinstall the switch back in the loop.
I'm still waiting to speak with the project engineer who shouldn't be opposed to this schedule unless there is
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4CDA620CCity...1/28/2011
Page 2 of 2
another factor I haven't considered.
Per
>>> Johnny Heine <johnny@melselectric.com> 11/5/2010 10:10 AM >>>
2 to 4 hours we will do the cabinet first and if we have time we will do
the pole if not we will do the pole on Friday
-----Original Message-----
From: Per Birdsall [mailto:PBIRDSALL@coppelltx.gov]
Sent: Friday, November 05, 2010 10:04 AM
To: Johnny Heine
Subject: Re: BETHEL AND DENTON-TAP SIGNALS
How long will the signal be off?
-----Original Message-----
From: Johnny Heine <johnny@melselectric.com>
To: Per Birdsall <PBIRDSALL@coppelltx.gov>
Cc: Dean Dumke <deand@JRJPaving.com>
Cc: Mark Obarr <mark@melselectric.com>
Sent: 11/5/2010 9:52:54 AM
Subject: BETHEL AND DENTON-TAP SIGNALS
We would like to schedule changing out the cabinet and signal pole next
Thursday 11th at 9:00 am. Will this be ok?
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4CDA620CCity...1/28/2011