ST0301A-CN101217REQUEST FOR INFORMATION (4.141 PROJECT: Bethel Road Reconstruction — Phase I PROJECT NUMBER: OWNER: City of Coppell CPL03423 CONTRACTOR: JRJ Paving, LP ENGINEER: Freese & Nichols, Inc. REFERENCE DATA: Specification Section No. Page No. Paragraph No. Drawing No. Detail description: CONTRACTOR REQUESTS: ❑ Information ❑ Interpretation ❑ Clarification for the items described below or in the attached material referenced below: - -- -RFI # 21 Bridge Drains In working towards finalizing out the bridge area, it was brought to my attention that at the drain in the bridge, there was some additional grate or something needed at the drain locations. In referencing ST -34, and meeting on the bridge with N TX Bridge and Keith Marvin, Coppell Engineering, we are trying to define what is actually required for this. Currently, the 3 drains have been installed, but the tubing that is called out has not. I have not in the past installed more than the formed concrete holes, but at this point need to know what needs to be done with the current conditions we have on site to either fix existing or is what exist acceptable. Please let me know what action needs to be taken. JRJ and their subcontractor will be working to final this project in the near future and so if an adjustment needs to be made, I would like to have review and response as soon as possible. CONTRACTOR'S PROPOSED SOLUTION: None. REQUESTED BY: Dean Dumke JRJ Paving, L.P. DATE: December 11, 2010 ENGINEER'S RESPONSE: ❑ Information ❑ Interpretation ❑ Clarification for the items described above or in the attached material referenced: Sheet ST -1 shows to reference "(SEE (FW) DRAIN SHEET) which is sheet ST -34. Detail ST -34 shows a metal box to be installed. It is our understanding this was not installed. If the drainage details were built per specification, except for the metal box, FNI is acceptable with this installation. RESPONSE BY: Antonio Diaz, P.E. (FNI) DATE: December 16, 2010 C: \DOCUME- 1 \radloo \LOCALS- 1 \Temp\XPgrpwise \Response to RFI 021 .docx 011) Keith Marvin - FW: Bethel Rd - Bridge Sidewalk Calculations, RFI 022 Page 1 From: Caleb Thornhill <bct @freese.com> To: Keith Marvin <kmarvin @coppelltx.gov> Date: 12/17/2010 8:24 AM Subject: FW: Bethel Rd - Bridge Sidewalk Calculations, RFI 022 Attachments: 20101217091641. pdf Keith, I've shown my calculations in red. I'm not sure where Dean is getting some of his lengths. Do you want me to put together a formal response to JRJ on this RFI? I'll have a response over to you guys this morning on RFI 21 - Bridge Drains. B. Caleb Thornhill, P.E. Freese & Nichols, Inc. 214 - 217 -2282 - - - -- Original Message---- - From: Dean Dumke [mailto:deand @JRJPaving.com] Sent: Thursday, December 16, 2010 10:19 AM To: Caleb Thornhill; Keith Marvin Subject: Bethel Rd - Bridge Sidewalk Calculations, RFI 022 Caleb, have personally measured the bridge side walk and attached are my calculations for the overrun of this quantity of 286 total square yards. will be submitting for payment on the November pay application. Thank you, Dean Dumke Sr Project Manager #469- 223 -7879 JRJ PAVING, L. P. Please consider the environment before printing this message. This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment, may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention, copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and delete all copies of the material from any computer. Thank you for your cooperation. , ; aDif— to JC S -A - 7 = rl ql I z Fq.. . 1 2Y, x? 4 t9(v V wk s' f = ►' ► ,'' `f► k S '• 22S'fL q r � ✓�Y (6 kRI 151 O F Is 510e- (L(3.S s vo 137 yd = iI �3 (c�Z. s xis Q -7 Yd� lZ�k? � i3�c Sf 151 O F Is 510e- ��9•� 7 = iI �3 lZ�k? � i3�c Sf ,fl .< I' . 2KrprL --� — z —./ l i �j A 3 7yd z T s -s�