Keith Marvin - Re: Damping Plate / update
From:
<RoadwaySolutions@aol.com>
To:
<kmarvin@coppelltx.gov>
Date:
9/8/2010 8:16 AM
Subject:
Re: Damping Plate / update
We will do.
Thanks
Morrie
In a message dated 9/8/2010 8:09:26 A.M. Central Daylight Time, kmarvin@coppelltx.gov writes:
Morrie,
I'll check with Per on the damping plates and get back to you.
As far as schedule goes, I think you still have about 45 days left in your contract, so we should be ok
with the delay. You will need to bag the heads when you get them installed.
Before we turn the signal on we will need to issue a notice in the local paper. Notices need to be
submitted by noon on Wednesday for a Friday publication. We'll take care of the notice, but I need to
know by noon on a Wednesday, we'll then flash the signal on the following Monday and Tuesday and
place it into operation on Wednesday.
Feel free to call Albert or I with any question.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> <RoadwaySolutions@aol.com> 9/8/2010 7:57 AM >>>
Good Morning Keith
Please advise if you are requiring Damping plate on all mast arms, if so we
will not be able to install it at the end of the arm but we can install it
5' away between two signal heads.
We have called city and verified that the service was inspected and green
tagged.
We have contacted Naztec for cabinet and at this time no cabinet is on hand
yet.
We will complete the mast arm installation as soon as the weather allows.
Thank you
Morrie