Attached is a schedule that I think we can build the job by, weather permitting. It does not
have any dates on it but is week by week with each location seperate.
Shane Huffman
RKM Utility Services, Inc.
General Superintendent
cell:214-236-5658
office:972-241-2621
fax:972-241-2624
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C87B776City_of...2/3/2011
Construction Work Schedule
Project Name:COPPELL 2009 STREET REPLACEMENT
RKM Utility Services Inc.
Work Order Number:
Contractor's Name:RKM UTILITY SERVICES, INC.
Proposed Work Schedule: Date of Contract:
As of:Reviewed by City Inspector:
Project Components:1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk1 wk
HERTZ ROAD (150days)
SEWER
WATER
EXCAV / LIME 1/2
PAVING / SIDEWALK
EXCAV / LIME 1/2
PAVING / SIDEWALK
STRIPING / CLEANUP
CLEAR CREEK (180 days)
SEWER
STORM DRAIN / INLETS
WATER
EXCAV / LIME 1/2
PAVING / SIDEWALK
EXCAV / LIME 1/2
PAVING / SIDEWALK
CLEANUP