(8/17/2011) Keith Marvin - Re: Street Improvement Project - Clear Creek LanePage 1
From: Keith Marvin
To:silvertulips
Date: 11/9/2010 2:48 PM
Subject: Re: Street Improvement Project - Clear Creek Lane
Attachments:Clear Creek Public Meeting agenda.doc
Ms. Davis,
The contractor, RKM Utilities, began work this week. The project involves the installation of new water, sewer, and storm
drainage lines, and the removal and replacement of the street and sidewalk paving. The contractor has 180 calendar days
to complete the project. It will be constructed in phases, and the road will remain passable during the construction.
I'm attaching a copy of the agenda from the meeting last week. If you would like to discuss this project in greater detail, or
see the plans for the work, please feel free to call me.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> silvertulips <silvertulips@gmail.com> 11/9/2010 9:39 AM >>>
Hello Mr. Marvin,
I was unable to attend the Nov 4 meeting between the residents of Cleart
Creek Ln, the Engineering staff, and the Ccontractor to learn about the
specifics of this project.
As such, would it be possible for you to provide the following information
via a response to this email?
1) What is the scope / nature of the improvements planned for this project?
2) What is the expected completion date of the project?
This information is very important to me because I work from home and need
to make plans for how to deal with the construction noise in light of my
conference call schedule.
Kind Regards,
Jennnifer Davis
474 Clear Creek Ln.
972-471-1152
MEMORANDUM
TO:
Tax 2009 Folder – Clear Creek
FROM:
Keith R. Marvin, P.E.
DATE:
11/04/2010
REF:
Public Meeting
Introductions
Keith Marvin – Project Engineer
Chris Seely – Design Engineer
Rick O’Dell – Construction Inspector
RKM Utilities – Shane Huffman (PM)
Residents?
Scope of Project:
New 8” water line – New services & meter cans.
New 8” Sewer line – new sewer services with cleanout at each Property line
New Paving – 6” thick with 8” lime stabilized subgrade 28’ back to back.
Sidewalk – 4’ both sides – Preserve the sidewalk that was replaced last year where possible
Funding Source:
¼ cent sales tax allocated to streets during November 2007 election
Contract amount - $587,597.50 with $40,000 potential bonus for early completion
Schedule
:
Project to begin on or about November 8, 2010. 180 Calendar Day max schedule, providing for
a May 2011 completion date. $40,000 allocated for early completion bonus. $1,000 per day
penalty for late completion.
Access:
One-way traffic during construction from Sandy Knoll to Willow Springs. Project will be
constructed in 4 phases (quarters).
Parking will not be permitted on the leg where the construction is taking place.
Contractor will maintain access for residents and emergency services.