ST8806-CS 890523 GINN, INC. CONSULTING ENGINEERS
May 23, 1989
Mr. Russell Doyle, P.E.
Coppell,P'o'City Box of CoppellTx478 75019
Re: Parkway Blvd. (CIP) - Half Street
Dear Mr. Doyle:
In response to your Handwritten Memorandum dated 5/14/89
regarding the above referenced subject, we wish to confirm that
our meeting with you is scheduled for 2:00 pm May 25, 1989 at
your office .... .:
We will have available at that time estimated project
construction costs based on CIP unit prices. We will also
provide you a set of plans for your use and review along with
tabulated quantities.
The actual project cost shall be a function of both time and
method by which the City chooses to initiate this construction
(ie., public bidding vs. change order). In order for the City to
proceed with a change order to an existing CIP project, the City
Council will have to determine that the public need is such that
the project be declared an emergency.
If the project is publicly bid, new contract documents and
specifications, advertising, bidding and the contract award
process will add additional engineering costs to this project
along with approximately 2-3 months of additional time.
If you have any questions prior to our scheduled meeting, please
call.
Sincerely, .. ~/
Kevin E. Peiffer, P.E.
KP/dsp
cc: H. Wayne Ginn, P.E.
File 89412
17103 Preston Road · Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900