Keith Marvin - RE: Kimbel Kourt-Elevations
From: "Adrian Bowman" <adrian@bowmanconstruction.com>
To:"'Michael Garza'" <mgarza@ci.coppell.tx.us>, "'Lee Halencak'"
<lee@bowmanconstruction.com>, "'Albert Samaniego'"
<ASAMANIEGO@ci.coppell.tx.us>, "'Keith Marvin'" <KMARVIN@ci.coppell.tx.us>,
"'Scott Latta'" <SLATTA@ci.coppell.tx.us>
Date: 7/16/2009 12:31 PM
Subject: RE: Kimbel Kourt-Elevations
We’ll barricade everything off tomorrow and get started with our sawing and removals. Our surveyor can’t get
back out there until tomorrow to revise the grades and mark the pavement removals.
Please let me know if this poses any problems.
Albert, can you please check and see if public works wants any of our asphalt millings? We should start milling
late tomorrow or first thing Monday. I also plan to get over there tomorrow to confirm the dirt dump location.
I’ll call you when I’m headed that direction.
Thanks,
Adrian
From: Michael Garza [mailto:mgarza@ci.coppell.tx.us]
Sent: Thursday, July 16, 2009 11:55 AM
To: Lee Halencak; Albert Samaniego; Keith Marvin; Scott Latta
Cc: adrian@bowmanconstruction.com
Subject: Re: Kimbel Kourt-Elevations
Lee,
What is your timeline for setting barricades and beginning the project? The updated plans are here at our
office, you can pick them up or call Albert and he can give them to you.
Thanks,
Mike
>>> On 7/14/2009 at 10:49 AM, in message <0KMS00J1X3XU0OI2@vms173005.mailsrvcs.net>, "Lee
Halencak" <lee@bowmanconstruction.com> wrote:
Gentlemen,
Our surveyor has been on site to stake the Kimbel Kourt Project. With the existing elevations on the south
end of the project at the tie in point and the proposed high point at station 2+00 the grade of the roadway is
approximately 0.2%. This is well below the 0.5% minimum set by the city. This presents a problem with
drainage and a solution needs to be made quickly in order of us to complete the project before the start of
school. We are at a standstill until the elevations can be worked out. Without proper elevations and a
solution we can not set grade and get anything installed. We are only being paid to go out there once and
we don’t want to have to do anything twice which could be the case if we continue before these elevations
are resolved. It is extremely important that a solution be in place very quickly.
A possible solution is to remove approximately 20’ of additional pavement on the south end and move the
proposed high point to the north. This will gain more of an elevation difference and get us closer to the 0.5%
grade. This solution would require that the approach to the pump station to be redesigned to remove
additional pavement.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4A5F1DB6City_...2/14/2011
Page 2 of 2
Our surveyor has been working with Scott and once he verifies the existing elevations we ask that solution
be put in place for us to continue our work.
Thanks
Lee M. Halencak, P.E.
Jim Bowman Construction Co., L.P.
1111 Summit Avenue, Suite 1
Plano, Texas 75074
Office: 972-423-1313
Fax: 972-423-9447