Loading...
SW0801-CN110214 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: SW08 -01 Denton Tap Infill CONTRACTOR: 3D Paving and Contracting, L.L.C. OWNER: City of Coppell CHANGE ORDER NO.: 2 DATE: 2 -14 -2011 Item Description Quantity Unit Unit Price Total ADD: 24 Clear, strip & grub 1 LS $4,042.50 $4,042.50 additional sidewalk area adjacent to Red Hawk Development 2 4" thick Reinforced 3785 SF $3.60 $13,626.00 Concrete Sidewalk 10 TxDOT PR1 Railing 15 LF $100.00 $1,500.00 25 4 Concrete footers at 1 LS $797.50 $797.50 Bridge 26 Concrete Flume at 1 EA $950.00 $950.00 580 S. Denton Tap 8 Barrier Free Ramp 4 EA $450.00 $1,800.00 Total Revision to Contract Amount $22,716.00 Original contract amount $ 231,754.00 Net increase by previous authorized Change Orders $16.44 Revised Contract amount prior to this Change Order $ 231,770.44 Net increase in contract amount $ 22,732.44 Revised contract amount $ 254,486.44 Cumulative increase in TOTAL change order amount (Percentage) 9.8% Net increase in contract time of completion 24 calendar days Revised Contract time of completion 179 calendar days 1 of 2 The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. P . 14.11 Recommended City Engineer ineer Date `./ /// Agree to by Contra or ate 2 4/21/ Accept by City Date 2 of 2