WA0301-BD050523 BID PROPOSAL
ADDENDA
ADDENDUM NO: ONE ISSUE DATE: May 23, 2005
PROJECT NAME: Loch Lane Water Line Installation BID DATE: May 26, 2005
WA 03 -01
LOCATION: COPPILL, TEXAS
ISSUED BY: City of Coppell
1. This addendum modifies and extends the requirements of the plans and construction
specifications for the above referenced project.
2. Staple this addendum to the inside of the rear cover of the construction specifications or bind
it into the construction specifications at the end of the Bid Proposal.
3. Note receipt of all addenda on the Bid Form located in the Bidding Documents, and also on
the outside cover of the envelope containing the Bid Documents.
CONSTRUCTION SPECIFICATIONS
1. Section 5- Description of Pay Items
2.14 Pay Item #I -14 — Abandon Existing 2" Water Line:
This work shall include abandoning the existing 2" water line as follows: Remove free
flowing liquids from the line and fill with grout. No portion of the 2" water line may be
left connected to the 16" main. Plug the portion of the main that fed the 2" line.
Measurement and Payment shall be made on the basis of the price bid per lump sum (LS)
to be total compensation for furnishing all labor, materials, tools, equipment and
incidentals necessary to complete the work.
• Clarification:
2.14 Pay Item #I -14 — Abandon Existing 2" Water Line:
This work shall include abandoning the existing 2" water line as follows: Remove free
flowing liquids from the line and plug any and all cut sections with a minimum of 12
inches of non shrink grout. No portion of the 2" water line may be left connected to the
16" main. Plug the portion of the main that fed the 2" line.
ADDENDUM NO: ONE Page 2 ISSUE DATE: May 23, 2005
PROJECT NAME: Loch Lane Water Line BID DATE: May 26, 2005
Measurement and Payment shall be made on the basis of the price bid per lump sum (LS)
to be total compensation for furnishing all labor, materials, tools, equipment and
incidentals necessary to complete the work.
2. General Questions for Clarification
There appears to be a conflict between the proposed 8" water line and the brick mailbox
at 604 Loch Lane. Is the mailbox to be relocated?
The water line is to be installed in front of the mailbox. The mailbox should be protected
from damage, but need not be relocated. The asphalt pavement repair shall be done in
accordance with Pay Item I -12. The actual quantity of repair will be paid at the unit price
established under this pay Item.
In several locations along the installation there are trees that overhang that will interfere
with the equipment required to install the water line. What are we to do about the trees?
All trees within the project area are to be protected to the greatest extent possible. The
successful bidder shall work with the city inspector to locate the line where it will have
the least impact to the adjacent property and trees. In the event tree trimming is
necessary it shall be done in a neat, professional manner. Any trimmings shall be hauled
off and properly disposed of by the contractor. Any cost associated with protecting or
trimming of trees shall be considered subsidiary to the installation of the water line, and
no additional payment will be made for this work.
The 1 " service line to the homes on the north end of the street appear to have bends on
them. Are these required fittings?
No special fittings are required for the bends shown. Services may be installed in a direct
path as long as they remain within the public Right of Way.
END OF ADDENDUM NO. ONE
This addendum forms a part of the contract documents. The original Contract Documents and
any prior addenda remain in full force and effect except as modified herein which shall take
precedence over any contrary provisions in the prior documents.
� OF T
i, � L� i *.' 00'.... .......
:
*: /\ * ■
Keith R. Marvin, PE.