Keith Marvin - Comparison between federal and city cost for Sandy Lake Road (ST99-02 B1)
From:Ken Griffin
To:Clay Phillips; Keith Marvin; Mario Canizares
Date:3/9/2011 3:43 PM
Subject:Comparison between federal and city cost for Sandy Lake Road (ST99-02 B1)
CC:Leslie Henderson
Attachments:txdot sandy lake.pdf
Clay
Attached is a chart comparing the cost to continue with Sandy Lake as a Federal project versus
reverting back to a city project. The cost difference is minimal, however, the real savings is in the
accelerated timeline. I'm unsure if you want to discuss this with Kenny Marchant. I've currently got
TxDOT on hold until we decide how to proceed.
ken g
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4D77A018City_...8/29/2011
Created 3 /9/2011
Sandy Lake between North Coppell and South Coppell Road
Save about $250,000 by reverting back to City standards and start
construction about 1.5 to 2 years sooner
Continue with
Revert back to
Federal Funding
City standards
(bid 2014)
(bid 2012)
$
1,000,000
Federal Funding
$
-
$
(200
City 20% share
$
-
$
800,000
$
-
$
(147,600)
Cost to redesign project to
$
(147,600)
Federal standards
$
652,400
$
(147,600)
$
( 101 157)
TxDOT costs, to date, for
$
(101,157)
review and oversight
$
551,243
$
(248,757)
$
9,594
Money already paid to
$
9,594
TxDOT
$
560,837
$
(239,163)
$
-
Scope change to revert back
$
(70,000)
to City standards
$
560,837
$
(309,163)
$
(120,000)
Scope changes for
$
-
environmental permit
$
440,837
$
(309,163)
$
(20,000)
Estimated additional
$
-
TxDOT charges
$
420,837
$
(309,163)
$
(22,000)
Estimated environmental
$
-
consultant fee
$
398,837
$
(309,163)
$
(4,517,900)
Estimated construction cost
$
-
to Federal standards
$
-
Estimated construction cost
$
(3,563,500)
to City standards
$
(4,119,063)
Total estimated cost
$
(3,872,663)
Save about $250,000 by reverting back to City standards and start
construction about 1.5 to 2 years sooner