May 18, 2011
Adrian Bowman
Jim Bowman Construction Co., L.P.
2716 S. Rigsbee Dr.
Plano, TX 75074
RE: MA 10 -06 Belt Line Road & Denton Tap Road
Brick Paver Replacement
NOTICE TO PROCEED WITH CONSTRUCTION
Dear Mr. Bowman:
This letter will serve as your official notice to begin work on the referenced project. For
purposes of the contract, your calendar days will start June 2nd, 2011. Forty Five (45)
Calendar Days were bid on this project for completion of work. Therefore, we anticipate
the project being complete by July 16, 2011. Please note that the incentive/ disincentive
bonus is tied to the number of days the intersection is closed to traffic from E. Belt Line &
Southwestern as well as the reduction in lanes along S. Belt Line & Denton Tap.
If you have any questions or need any additional information please feel free to contact Rick
O'Dell, Construction Inspector at (972) 304 -7090.
Sincerely,
George Marshall, P.E.
Civil Engineer
Office: 972/304 -3562
Fax: 972/304 -7041
gmarshall(d coppelltx.gov
cc: Kenneth Griffin, P.E., Director of Engineering/Public Works
Rick O'Dell, Construction Inspector
A FAMILY COMMUNITY FOR A LIFETIME
255 PARKWAY * P.O. BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * WWW.COPPELLTX.GOV
Denton Tap & Sandy Lake Brick Paver Replacement JBCC Project No. 876
Construction Schedule Wed 5/18/11
Jim Bowman Construction Company, LP
ID Task Name Duration Start Finish Predecessors 29, '11 Jun 5, '11 ' Jun 12, '11 _ Jun 19, '11 Jun 26, '11
TWTFSSMTWTFSS ;MTWT'FSSMTWTFSSMTWT
1 Belt Line & Denton Tap Brick Paver Replacement 28 days Thu 6/2/11 Wed 6/29/11 ® V
2 Detour Layout / Sign Distribution 2 days Thu 6/2/11 Fri 6/3/11
3 Temporary Signal Setup 2 days Thu 6/2/11 Fri 6/3/11 MO
.v
4 Temporary Median Crossover 1 day Thu 6/2/11 Thu 6/2/11
5 Phase I - Inside Lanes 10 days Mon 6/6/11 Wed 6/15/11 2,4 _
6 Detour Setup / Lane Closures 0.5 days Mon 6/6/11 Mon 6/6/11 �?-
7 Sawing 0.25 days Mon 6/6/11 Mon 6/6/11 6 Ca l
8 Pavement / Paver Removals 2.25 days Mon 6/6/11 Wed 6/8/11 7
9 12" Stamped RC Pavement 4 days Thu 6/9/11 Sun 6/12/11 8
10 12" RC Pavement (High Early) 3 days Mon 6/13/11 Wed 6/15/11 9
11 Phase II - Outside Lanes 8 days Thu 6/16/11 Thu 6/23/11 5
_
12 Barricades / Traffic Switch 0.25 days Thu 6/16/11 Thu 6/16/11
� 13 Sawing 0.25 days Thu 6/16/11 Thu 6/16/11 12 I-
14 Pavement / Paver Removals 1.5 days Thu 6/16/11 Fri 6/17/11 13
ifIlliii
15 12" Stamped RC Pavement 2 days Sat 6/18/11 Sun 6/19/11 14
16 12" RC Pavement (High Early) 3 days Mon 6/20/11 Wed 6/22/11 15
17 Open Traffic / Remove Detour 1 day Thu 6/23/11 Thu 6/23/11 16
18 Pavement Markings 1 day Fri 6/24/11 Fri 6/24/11 11
19 BFRs & Sidewalks 4 days Fri 6/24/11 Mon 6/27/11 11 ------
20 Median Crossover Removal 1 day Tue 6/28/11 Tue 6/28/11 19 okii
21 Clean -up / Punchlist 1 day Wed 6/29/11 Wed 6/29/11 20 ow
JIM BOWMAN CONSTRUCTION COMPANY L.P
2716 S. Rigsbee Dr. • Plano, Texas 75074 • (972) 423 -1313
May 18, 2011
Mr. George Marshall, P.E.
City of Coppell
255 E. Parkway Blvd.
Coppell, TX 75019
Re: JBCC Project #895 — Belt Line & Denton Tap Brick Paver Replacement
We offer the following list of personnel for emergency contact purposes:
Name Title Cell Phone Home
Adrian Bowman Assistant GM (214) 535 -6588 (972) 208 -6018
Vicente Murillo Paving Superintendent (214) 535 -2804 (972) 487 -9362
Jim Bowman General Manager (214) 926 -7398 (972) 509 -1599
Dusty DeFury Estimator (214) 926 -9554 (903) 267 -0533
Subcontractor Type of Work Phone
Metroplex Pavement Markings Pavement Markings (972) 399 -3500
North TX Bomanite Stamped Concrete (972) 484 -8465
Buyers Barricades Barricades / Detours (817) 535 -3939
Horizon Signals (via Buyers) Temporary Signals (610) 256 -6007
Please call if you have any questions.
Sincerely,
•.rianpowman
Assis nt General Manager
Jim Bowman Construction Co., L.P. LETTER OF TRANSMITTAL
2716 S. Rigsbee Dr.
Plano, TX 75074
(972) 423 - 1313 Date: 18- May -2011 Job No: 895
Attention: Mr. George Marshall, P.E.
Regarding: Delt Line & Denton Tap Brick Paver Replacement
To: City of Coppell
Engineering Department
WE ARE SENDING YOU: ❑ Attached ❑ Under seperate cover via the following items:
❑ Shop Drawings ❑ Prints ❑ Plans ❑ Samples ❑ Specifications
❑ Copy of Letter ❑ Change Order ❑
COPIES DATE NO. DESCRIPTION
1 5/18/11 Emergency Contacts / Subcontractor Listing
4 5/18/11 Project Schedule
THESE ARE SUBMITTED (as checked below)
❑ For approval ❑ Approved as submitted ❑ Resubmit copies for approval
El For your use ❑ Approved as noted ❑ Submit copies for distribution
El As requested ❑ Returned for corrections ❑ Return corrected prints
❑ For review and comments ❑
❑ FOR BIDS DUE 2010 ❑ PRINTS RETURNED AFTER LOAN TO US
REMARKS
COPY TO: SIGNED: Adrian Bowman owman