Loading...
WA9601B-CS 990106, . 5 SHIMEK, JACOBS & FINKLEA, L.L.P. CONSULTING ENGINEERS 8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900 MEMORANDUM From: Gary C. Hendricks Date: January 6, 1999 Subject: Sandy Lake Road Water Line Ken: Thanks for the mark-ups you provided us from Lone Star Gas for the Sandy Lake Road Water Line Project. For your information, we located the existing gas lines on the plans to the best of our ability based on our field surveys. Once the alignment and grade of the proposed water line was set and met with the City' s satisfaction, we forwarded two preliminary sets to each utility company for their review and comment. That was done on February 23, 1998 (see attached letter to LSG as an example). You should have received copies of those letters. The only response we received from was from Lone Star Gas Transmission on March 5, 1998. We made the corrections requested by Mr. T.W. Rudd. In October of 1998, we set had a final set of plans ready to bid and had set a preliminary bid date for early November. Having not heard from a majority of the utility companies, we sent out another letter informing them of the project and providing them with final plans. That letter went out on October 3, 1998 (see attached). Again, we have had no response other than the set of mark-ups from Lone Star Gas you provided us today. Upon closer review of the plans, I believe you will see where we have indicated the general location of the gas line in both the plan and profile views, where we thought them to be, and have provided warning notes and phone numbers on the plans. It does not appear this will create any significant or unusual problems for this project; however, we will provide these mark-ups to the contractor at the pre-constmction conference. GCH SHIMEK, JACOBS & FINKLEA, L.L.P. CONSULTING ENGINEERS 8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900 ROSS L. JACOBS, P.E. RONALD V. CONWAY, P.E. JOHN W. B1RKHOFF, P.E. JOE n. CANTER, P.E. February 23, 1998 GARY C. HENDRICKS, P.E. i. C. FINKLEA, P.E. Lone Star Gas Mr. Kenneth Govan Post Office Box 306 Lewisville, Texas 75067 Re: City of Coppell Sandy Lake Road Water Line (Denton Tap Road to the Wagon Wheel Ranch Elevated Tank) Gentlemen: We are enclosing two sets of preliminary construction plans for the City of Coppell, Sandy Lake Road Water Line project, from Denton Tap Road to the proposed Wagon Wheel Ranch Elevated Storage Tank. These sets are for your review and comment. We have located existing utilities to the best of our knowledge based on information gathered during our field surveys and provided by the City. A large portion of this project is to be constructed in easements on private property which minimizes the potential conflicts. Nonetheless, please review the plans carefully and notify us &any revisions required or conflicts anticipated by return one mark- up set back to our office. The City of Coppell expects to advertise this project for bids early this spring with construction to start before this summer. If you have any questions, or need additional information, please do not hesitate to contact us. Sincerely yours, Gary C. Hendricks, P.E. Enclosures cc: Mr. Kenneth M. Griffin, P.E. Mr. Jeff Curry, TU Electric / Lone Star Gas ~] 50\l ettersXcorresXl sg_l ,do~ SHIMEK, JACOBS & FINKLEA, L.L.P. CONSULTING ENGINEERS 8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900 ROSS L. JACOBS, P.E. RONALD V. CONYqAY, P.E. JOHN W. BIRKHOFF, P.E. JOE R. CARTER, P.E. October 3, 1998 GARY C. HENDPdCKS, P.E. I. C. FINKLEA, P.E. Lone Star Gas Mr. Kenneth Govan Post Office Box 306 Lewisville, Texas 75067 Re: City of Coppell Sandy Lake Road Water Line (Wagon Wheel Ranch Elevated Tank to Denton Tap Road) Gentlemen: We are enclosing one set of final construction plans for the City of Coppell, Sandy Lake Road Water Line project, from Denton Tap Road to the proposed Wagon Wheel Ranch Elevated Storage Tank. These sets are for your use during construction of this project and replace the set we provided you in February of this year for your review and comment (see attached letter). As of the date of this letter we have yet to receive your review comments. Nonetheless, we have located existing utilities to the best of our knowledge based on information gathered during our field surveys and provided by the City. A large portion of this project is to be constructed in easements on private property which minimizes the potential conflicts. At this stage, the City intends to award a construction contract for this project in early November, 1998 with construction to begin by January, 1999. We will keep you informed of the project schedule and notify you of the time and date of the pre-construction conference. If you have any questions, or need additional information, please do not hesitate to contact us. Gary C. Hendricks, P.E. Enclosures cc: Mr. Kenneth M. Griffin, P.E. Mr. Jeff Curry, TU Electric / Lone Star Gas j~:~oppell\96-150Metters\corresXlsg_l_Edoc