RIVERCHASE ELEVATED SIDEWALK PROJECT
BID Q- 0902 -01
OCTOBER 8, 2002
Simmons
Green Scaping Rebcon Builders Jim Bowman Linder Smith
Construction Construction Contractors
Total Base Bid $135,737.00 $177,256.50 $159,308.00 $179,881.00 $169,552.00 $176,745.00
Ca lender Days 90 90 140 120 100 150
RIVERCHASE ELEVATED SIDEWALK PROJECT # SW 00 -01
BASE BID
Item Quantity Unit Description Green Scaping Simmons Builders Linder Smith Contractors Rebcon Jim Bowman
Construction Construction
Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price
1 -1 677 CY Earth & Borrow 30.00 20,310.00 22.00 14,894.00 20.00 13,540.00 6.00 4,062.00 15.00 10,155.00 47.00 31,819.00
1 -2 147 LF Silt Fence 2.00 294.00 3.00 441.00 3.00 441.00 2.00 294.00 3.50 514.50 2.00 294.00
1 -3 12 EA Hay Bale Check Dam 25.00 300.00 15.00 180.00 17.00 204.00 300.00 3,600.00 55.00 660.00 10.00 120.00
1-4 36 LF Concrete Sawcut 10.00 360.00 10.00 360.00 12.00 432.00 3.00 108.00 15.00 540.00 4.00 144.00
1 -5 283 SY 4" Concrete Sidewalk 36.00 10,188.00 50.00 14,150.00 47.00 13,301.00 27.00 7,641.00 35.00 9,905.00 27.00 7,641.00
1-6 2 EA Barrier Free Ramp 1200.00 2,400.00 777.00 1,554.00 740.00 1,480.00 1,000.00 2,000.00 1700.00 3,400.00 600.00 1,200.00
1 -7 497 LF 8' Elevated Sidewalk/Foundation 205.00 101,885.00 257.00 127,729.00 282.00 140,154.00 320.00 159,040.00 306.00 152,082.00 279.00 138,663.00
Calendar Days 90 140 100 150 90 120
TOTALS $135,737.00 $ 159,308.00 $ 169,552.00 $ 176,745.00 $ 177,256.50 $ 179,881.00