George Marshall - RE: Schedule for Belt Line Road Pavement Investigation
From: George Marshall
To: Doug Ziolkowski
Date: 5/2/2011 11:45 AM
Subject: RE: Schedule for Belt Line Road Pavement Investigation
http://www.txdot.gov/insdtdot/orgchart/cmd/cserve/standard/toc.htm
>>> "Doug Ziolkowski" <DZiolkowski@gmeconsult.com> 5/2/2011 11:18 AM >>>
George: Do you have a copy of TxDOT detail TCP 1-4a. I am not familiar with this since we don't often drill in
roads. Doug!
From: George Marshall [mailto:gmarshall@coppelltx.gov]
Sent: Monday, May 02, 2011 11:18 AM
To: Doug Ziolkowski
Cc: Per Birdsall
Subject: Re: Schedule for Belt Line Road Pavement Investigation
Doug,
Thank You for the schedule. We will make sure the arrow board is available for use. As called for in the contract,
you will be providing the temporary traffic control. I would like to point to the TxDOT detail TCP 1-4a to be used
as a guide. Belt Line road is posted at 45 MPH. For file purposes, I would like to have you fill out a permit &
attach your TCP. (See attached). Please ignore the fee. This form was developed for franchise utilities.
What time tomorrow were you thinking about meeting? I have a 9:30 meeting that will last till 12 or so. I would
like for Per to be at this meeting if available.
Thank You, George
George Marshall, PE
City of Coppell
Engineering
972-304-3562
>>> "Doug Ziolkowski" <DZiolkowski@gmeconsult.com> 5/2/2011 10:03 AM >>>
Good morning George: I was able to get a lot of work caught up last week and should now be able to devote the
proper energy to the Belt Line Road pavement investigation. As you requested, I have determined a preliminary
schedule of work that GME will perform:
Proposed Work Schedule:
Item No. Work Activity Duration of Work Proposed
Work Dates
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4DBE994BCity_...6/17/2011
Page 2 of 3
1) Determine Boring Locations on Plans 2 hours May 2,
2011
2) Meet with City of Coppell (George)
to approve boring locations 2 hours May 3,
2011
3) Mark boring locations on Belt Line Road 6 hours May 4,
2011
4) Call Digtess for Utility locates and markings 2 Working Days May 4
through May 6, 2011
5) Core Pavement and Drill Test Borings 3 Working Days (or less) May
10 through May 12, 2011
6) Assign Lab Tests and Perform Lab Testing 10 Working Days (or less) May
13 through May 26,2011
7) Anaylyze Data and Prepare Report 10 Working Days (or less) May
27 through June 10, 2011
The schedule of work described above is in accordance with our project schedule as outlined in our proposal
P11.04.0030 dated March 3, 2011.
I have the drilling subcontractors notifed of the schedule and they are checking to be sure it works with them.
We will need to have the traffic board signs available during the time period proposed.
Please review the schedule and provide any comments.
Thanks Doug!
Douglas P. Ziolkowski, P.E.
President
GME Consulting Services, Inc.
2530 Electronic Lane, Suite 710
Dallas, Texas
Phone: 214-351-5633
Fax: 214-351-5680
__________ Information from ESET NOD32 Antivirus, version of virus signature database 6088 (20110502)
__________
The message was checked by ESET NOD32 Antivirus.
http://www.eset.com
__________ Information from ESET NOD32 Antivirus, version of virus signature database 6088 (20110502)
__________
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4DBE994BCity_...6/17/2011
Page 3 of 3
The message was checked by ESET NOD32 Antivirus.
http://www.eset.com
__________ Information from ESET NOD32 Antivirus, version of virus signature database 6088 (20110502)
__________
The message was checked by ESET NOD32 Antivirus.
http://www.eset.com
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4DBE994BCity_...6/17/2011