MA0401-CS060307
PRESS RELEASE
DATE: March 7, 2006
Rehabilitation of Asphalt Streets
in
Northlake Woodlands Subdivision
(Oakcrest Ln., Hidden Valley Dr., Sandy Oak Ln.,
Oakbrook Dr., Rolling Hills Circle and Glencrest Circle)
The city budgeted funds this year in the Infrastructure Maintenance Fund (IMF) for rehabilitation
of asphalt streets within the Northlake Woodlands Subdivision. A Dallas County crew will be
repairing and overlay the streets in this area beginning Monday, March 13, 2006 and continuing
through April 2006.
Also, the city's concrete contractor is continuing to work on the balance of the Northlake
Woodlands Phase 7 curb and gutter rehabilitation to prepare for Dallas County to pave those
streets.
Two-way traffic will be maintained during construction; however, you may experience delays
and inconveniences.
Thank you in advance for your patience during this project. If you have any questions please
contact Garreth Campbell, the City Inspector at 972/304-3685 or the Engineering Department at
972/304-3679.
CURRENT CONSTRUCTION PROJECTS
Construction / Road Closures
TOWN CENTER BOULEVARD
(Between Wendy's and the YMCA) (est. time - Spring Break March 13 thru
March 19, 2006)
Town Center Blvd., between Wendy's Restaurant and the YMCA, will be
completely closed to traffic during Spring Break beginning Monday, March
13 through Sunday, March 19, 2006 for pavement repairs. You will need to
seek alternate routes. If you have any questions please contact Garreth
Campbell, City Inspector, at 972/304-3685 or the Engineering Department at
972/304-3679.
#ST 93-01 - EAST SANDY LAKE RD.
Kimbel Kourt to east city limits) (est. time - March 2005 thru July 2006)
(
The project consists of the reconstruction of the existing 2-lane asphalt
road to a 4-lane divided roadway with improved drainage. Construction
began in March 2005 and will continue through the 3rd Quarter of 2006. City
Council awarded the contract for the construction of this project to Tiseo
Paving Company. If you have any questions please contact Garreth
Campbell, City Inspector, at 972/304-3685 or the Engineering Department at
972/304-3679.
Riverchase Dr. will be closed to all through traffic at East Sandy Lake Rd.
during the week of March 13th to facilitate the transition to the new paving
for the east and west bound traffic flow. After the switch of traffic, the
contractor will start filling on the south side and in April should begin his
subgrade work and start paving shortly thereafter. Two-way traffic will be
maintained; however, you may experience construction delays and
inconveniences.
#ST 99-02 - WEST SANDY LAKE RD. Phase A
(SH 121 to Coppell Rd. North) and ROYAL Ln. (Northpoint to Sandy Lake
Rd.) (est. time - January 2006 thru November 2006)
A contract for Sandy Lake Rd. was awarded to Tiseo Paving Company in
December 2005. The project consists of the reconstruction of the existing
2-lane asphalt road to a 4-lane divided roadway with related drainage, water
and sidewalk improvements. Also, traffic signals will be installed on Sandy
Lake Rd. at Royal Ln., Freeport Pkwy., and N. Coppell Rd., and the
construction of two additional lanes to make Royal Ln. a 4-lane divided
roadway. The construction will take place on the south side of the roadway
with the two lanes being constructed and then traffic being switched over
to the new lanes for the removal of the existing asphalt roadway and
construction of the remainder of the road.
Two-way traffic along West Sandy Lake Road will be maintained at all
times. However, North Coppell Road, at its intersection with West Sandy
Lake Road, will be completely closed to traffic during Spring Break (March
11 thru 19) for the contractor to install drainage pipe. You may experience
construction delays and inconveniences beginning January 2006 through
November 2006. If you have any questions please contact Larry Davis, City
Inspector, at 972/304-3684 or the Engineering Department at 972/304-3679.
Northlake Woodlands Rehabilitation of Asphalt Streets
(Oakcrest Ln., Hidden Valley Dr., Sandy Oak Ln., Oakbrook Dr., Rolling Hills
Circle and Glencrest Circle) (est. time - March 13, 2006 thru April 2006)
The city is continuing with the rehabilitation of streets in Northlake
Woodlands. A Dallas County crew will be repairing and overlaying the
streets in this area beginning Monday, March 13 and it is expected to take
approximately 4 weeks.
The city's concrete contractor, Pavement Services, is continuing to work
on the balance of the Northlake Woodlands Phase 7 curb and gutter
rehabilitation in preparation for Dallas County crews to pave those streets.
Two-way traffic will be maintained during construction; however, you may
experience delays and inconveniences. If you have any questions please
contact Garreth Campbell, City Inspector, at 972/304-3685 or the
Engineering Department at 972/304-3679.
#WA 97-01 - BELT LINE ROAD / DENTON TAP ROAD 16-Inch WATER LINE
IMPROVEMENTS
(Airline Drive to Bethel Road) (est. time - November 2005 thru April 2006)
The construction of the waterline begins at the intersection of Belt Line Rd.
and Airline Dr. and goes north to the intersection of Denton Tap Rd. and
Bethel Rd. City Council awarded the contract for construction of this
project to J.T. Dersner, Inc. Construction started in November 2005 and will
take approximately 150 days to complete. North and south bound lanes on
Belt Line / Denton Tap (between Airline and Bethel) will be closed at
various times and locations in order to perform the work. You will
experience construction delays and inconveniences. If you have any
questions please contact the Engineering Department at 972/304-3679.
#ST 99-05 DR - BETHEL ROAD I DRAINAGE PHASE 'A' IMPROVEMENTS
(Grapevine city limit line to Freeport Parkway) (est. time - December 2005
thru April 2006)
This project generally consists of construction of a multi-barrel box culvert
from the intersection of Freeport Pkwy/Bethel Rd. southward to the existing
creek. A headwall will be constructed at the creek and gabions will be
provided for slope stabilization along the creek bank. Also, grading will
take place from the outfall to the south side of the existing culverts beneath
Bethel Rd. immediately east of Loch Lane. City Council awarded the
contract for construction of this project to Craig Olden, Inc. and
construction started in December 2005. If you have any questions please
contact the Engineering Department at 972/304-3679.
STATE HIGHWAY 121 BYPASS
(Dallas County Line to IH 35E)
This project consists of two separate projects both being constructed by
the Texas Department of Transportation (TxDOT). One section is from Lake
Vista Drive eastward to the north side of IH 35E; and the other section is
from Lake Vista Drive westward to the split of S.H. 121 Bypass and S.H. 121
Business (near the Grapevine, Coppell, Lewisville meeting point).
VERIZON Communications Upgrade
Verizon has substantially completed upgrading their system in Coppell to
state-of-the-art fiber optic technology. The entire city was ultimately "re-
wired" during this upgrade project. The project was reviewed and permitted
through the City of Coppell Engineering Department. ;
#SS 99-01 - DEFOREST ROAD LIFT STATION IMPROVEMENTS
The overall design of the DeForest Rd. Lift Station Improvements consist of
a new lift station, the rehabilitation of the Sandy Lake Rd. lift station, and
force main improvements. If you have any questions please contact Rick
O'Dell, City Inspector at 972/304-7090 or the Engineering Department at
972/304-3679.
This project is being constructed as four separate projects:
/ Deforest Road and Sandy Lake Road Lift
1.UNDER CONSTRUCTION
Station Improvements
A contract for the construction of a new lift station at Deforest Rd. and the
rehabilitation of the Sandy Lake Rd. lift station was awarded to CanFer
Construction Company in October 2004. Construction of this project began
in November 2004 and anticipated completion of the project is the 2nd
Quarter of 2006.
2./ Force Main Line D
CONSTRUCTION COMPLETE
As part of the upgrades to our sanitary sewer system, a new sanitary sewer
force main was installed in the median of MacArthur Blvd. from Deforest
Road to Village Parkway. At Village Parkway, it proceeds in an easterly
direction to the city's pump station, and then proceeds southerly across
Sandy Lake Road to the existing sanitary sewer lift station, behind the
vacant shopping center at the southeast corner of MacArthur and Sandy
Lake.
3./ Force Main Lines / A & B
CONSTRUCTION COMPLETE
Force Main Lines 'A' & 'B' was generally constructed in the median of
MacArthur Boulevard, from Condor Drive to Belt Line Road, and on city
owned property.
4. / Force Main Line C
CONSTRUCTION COMPLETE
PROJECTS IN DESIGN
#ST 99-02 - WEST SANDY LAKE RD.
Phase A - SANDY LAKE RD. / under construction
(SH 121 to Coppell Road North) and ROYAL LANE (Northpoint to Sandy
Lake Road)
Phase B - SANDY LAKE RD.
(Coppell Road north to Denton Tap Road)
A design contract for Sandy Lake Road was awarded to Teague, Nall and
Perkins, Inc. on December 12, 2000. The project consists of the
reconstruction of the existing 2-lane asphalt road to a 4-lane divided
roadway with improved drainage. The project is in the preliminary design
phase. Construction of the improvements is anticipated to start in 4th
Quarter 2008.
#ST 99-05 - BETHEL RD. I
(West City Limits to Freeport Parkway)
A design contract for Bethel Road was awarded to TranSystems Corporation on February
13, 2001. The project consists of the widening of the existing 2-lane asphalt road to a 4-
lane divided roadway. The project also includes a detailed drainage study to determine
how to accommodate the future drainage associated with the large undeveloped property
at the southwest corner of Royal Lane and Bethel Road, and design of the required
drainage improvements. The contract for construction of Phase 'A' of the drainage
improvements has been awarded and is anticipated to start in the 3rd Quarter of 2006.
#ST 03-01 - BETHEL RD. II
(Bethel Road from Denton Tap Rd. to Freeport Pkwy. and Coppell Road from Bethel Rd.
north to Cooper Ln.)
A design contract for Bethel Road was awarded to Freese & Nichols, Inc. at the May 27,
2003 City Council meeting. The project consists of the reconstruction of the existing 2-
lane asphalt road, streetscape improvements in the historic downtown area, storm drain
improvements, and the replacement of water lines. The project is in the design phase and
the construction plans are 60% complete. Construction of the improvements is anticipated
to start in the 3rd Quarter of 2007.
#ST 00-03 - COPPELL RD.
(Sandy Lake Rd. to Cooper Ln.)
A design contract for Coppell Road was awarded to Huitt-Zollars, Inc. at the June 24, 2003
City Council meeting. The project consists of the reconstruction of the existing 2-lane
asphalt roadway to a 2-lane undivided roadway, the addition of sidewalks along both sides
of the road, and improved drainage. The project is in the design phase and construction of
the improvements is anticipated to start in the 2nd Quarter of 2007.
Engineering/Public Works Department
Road Construction / Road Closures
During the week of Spring Break (March 11 through March 19) several roads in the city will be
closed for construction.
North Coppell Road, between Eastwick Dr. and West Sandy Lake Rd., will be completely closed to
traffic for the installation of drainage pipe associated with the West Sandy Lake Road project.
Town Center Boulevard, between Wendy's Restaurant and the YMCA, will be completely closed to
traffic for pavement repair.
Riverchase Drive will be closed to all through traffic at East Sandy Lake Rd. to facilitate the
transition to the new paving for the east and west bound traffic flow of East Sandy Lake Rd.
Northlake Woodlands Rehabilitation ( Oakcrest Ln., Hidden Valley Dr., Sandy Oak Ln., Oakbrook
Dr., Rolling Hills Circle and Glencrest Circle) will continue with a Dallas County crew starting
Monday, March 13 and continuing through April. Two-way traffic will be maintained during this
construction.
You may experience construction delays and inconveniences in these areas.
For more information on these projects and other construction projects within the city of Coppell