Loading...
SW08/09-CS090608 July 22, 2011 Roger Dupre Styles Contracting 5625 Egg Farm Rd, Ste 1120 Keller TX 76244 RE: Contract Performance / Sidewalk Repair Project Dear Mr. Dupre: This letter is written to document an incidence of contract noncompliance at 774 Pelican Drive. According to Specification 16 of the contract, “once work in one area has commenced, it shall be completed and restored within 10 days.” Your company has 10 days from when the existing sidewalk is removed to the time it is replaced and backfilled with all forms and associated mess cleaned up. It took almost a month and numerous contacts (between the resident, our personnel and your personnel) from the time the sidewalk at the above address was poured until our streets crew finally took it upon themselves to remove the forms, trash and construction tape left behind by your crew. We understand that complaints on this kind of project will arise, however we also expect a better response from you when we call a problem to your attention. Sincerely, Keith R. Marvin, P.E. Project Engineer Office 972/304-3681 kmarvin@ci.coppell.tx.us cc: Kenneth M. Griffin, P.E., Director of Engineering/Public Works Glenn Hollowell, P.E., Assistant Director of Public Works Albert Samaniego, Construction Inspector