Kimbel 7&8-CS071227
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
PD-223R-C, Chase Bank,
zoning change request from PD-223-C (Planned
Development-223-Commercial) to PD-223R-C (Planned Development-223
Revised-Commercial) to attach a Detail Site Plan to allow the development of a
3,848-square-foot bank with four drive-thru lanes on 0.70 acres of property,
located at the southeast corner of MacArthur Boulevard and Village Parkway at
the request of Mathew Cragun, O’Donnell Engineering.
STAFF REP.: Marcie Diamond PROJECT ID# PD-07-0090
DRC DATE:December 27, 2007 - January 3, 2008
CONTACT:
Kenneth M. Griffin, P.E., Dir.of Engineering/Public Works 972/304-3686
FINAL REVISED
COMMENT STATUS: PRELIMINARY
AFTER P&Z
1. Change the city to Coppell on all pages.
2. If lime stabilization is not going to be used for the paving, a waiver request must be
submitted by the engineer along with the geotechnical report and the thickness of concrete
increased by 1”.
3. The retaining wall is in conflict with the sanitary sewer on the east side of the project.
The engineered retaining wall design will need to be submitted to Engineering Department
during the plan review process.
4. Place/ Locate Fire Hydrant on Plan.
5. Water mains shall be PVC.
6. Water Services should be 1 inch type K copper stop.
7. Storm sewer should be RCP class III.
8. Redwood expansion filler should be used on sidewalk expansion joint.
9. It appears that a set of plans was submitted with the DRC information. These plans
should not be considered submission for engineering approval. Plans for review should not
be submitted until approval from Planning and/or City Council is granted.