Keith Marvin - Re: Fwd: FW: alex canal
From:Ken Griffin
To:John Elias; Keith Marvin; Michael Garza; Per Birdsall
Date:6/29/2011 4:16 PM
Subject:Re: Fwd: FW: alex canal
Keith
I have a couple of questions: 1) Will they be performing any underwater surveying to ascertain the
actual canal bottom conditions before they design a solution? 2) Will they be performing any testing
during their design phase so assist them in footing design for a new wall? Paragraph 3 under Basic
Services seems to place the testing requirement on the city.
ken g
>>> Keith Marvin 6/29/2011 3:40 PM >>>
Attached is a proposed scope and fee for the Alex Canal project. Please take a look at this
and let me know your thoughts.
Thanks,
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Mark Holliday" <mholliday@tnp-online.com> 6/29/2011 9:45 AM >>>
Good morning Keith.
Attached is a draft contract proposal for the Alex Canal project for your review.
Regarding the CAD services work, did you decide if it was to be a stand alone contract or
amendment to the existing contract for those streets?
Mark
-----Original Message-----
From: TNP [mailto:matkins@tnp-online.com]
Sent: Wednesday, June 29, 2011 9:37 AM
To: Mark Holliday
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4E0B4FECCity_o...8/5/2011
Page 2 of 2
Subject: alex canal
Please open the attached document. This document was digitally sent to you using an HP
Digital Sending device.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4E0B4FECCity_o...8/5/2011