(8/8/2011) Keith Marvin - RE: Bethel Road IIPage 1
From: Keith Marvin
To:Richard.Brewster@oncor.com
Date: 6/3/2010 3:08 PM
Subject: RE: Bethel Road II
Yes, we met with Scott Beamis out there this morning. It looks like it will work out for us.
Thanks for your help.
Keith
>>> <Richard.Brewster@oncor.com> 6/3/2010 3:05 PM >>>
Did someone from Oncor make contact with you in regards to this issue?
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Tuesday, June 01, 2010 10:26 AM
To: Brewster, Richard
Subject: Fwd: Bethel Road II
Richard,
This is the schedule JRJ is looking at for the possible power shut down
we talked about. Please pass this along to the operations folks with my
name and phone number.
Thanks,
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Marty Murphy" <Martym@JRJPaving.com> 5/28/2010 12:34 PM >>>
Here is the schedule we are looking at for the bridge to help facilitate
the coordination meeting for power shut down by Oncor;
6/14 - shut down road, demo bridge
6/21 - channel excavation, drill piers (need power shut down 6/21-6/25)
7/5-7/26 - complete channel excavation, pour abutments and caps and rip
rap
8/2 - set beams and panels ( need power shut down 8/2-8/6)
8/9-9/7 - complete bridge and open to two lanes of traffic
Please review and see if we can set up a meeting for next Tuesday in the
afternoon if possible to discuss in the field with Oncor.
Thanks for your help.
Marty
(8/8/2011) Keith Marvin - RE: Bethel Road IIPage 2
Confidentiality Notice: This email message, including any attachments,
contains or may contain confidential information intended only for the
addressee. If you are not an intended recipient of this message, be
advised that any reading, dissemination, forwarding, printing, copying
or other use of this message or its attachments is strictly prohibited. If
you have received this message in error, please notify the sender
immediately by reply message and delete this email message and any
attachments from your system.