(8/8/2011) Keith Marvin - Re: Follow UpPage 1
From: Keith Marvin
To:pajares, luis
CC:terry@theholmesbuilders.com
Date: 7/29/2010 5:45 PM
Subject: Re: Follow Up
Attachments:CO6 Special Wall Section N Wall.pdf; Sound Wall.pdf
Luis,
I apologize for not getting back with you sooner, I've been on vacation for the last week or so. I have gotten responses
from both the engineer and the contractor. The engineer has proposed an additional fee of $6,000 for the design of the
combination retaining wall and screening wall. The contractor has provided a cost proposal of $37,000 for this wall. We
would realize a savings of $17,000 under the contract for not building the retaining wall/rail, resulting in a net change of
$20,000.
This change would result in a cost of approximately $26,000. If this is something you want to pursue, we will need to work
out some sort of comprehensive agreement to take to City Council for approval. Give me a call when you have a chance
and we can discuss it.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> luis pajares <lpajares3@gmail.com> 7/20/2010 6:59 AM >>>
Hi Keith,
where are we with the plan for the retaining wall? Have you heard back from
the engineers on a scope of work yet? Might be good to talk.
thanks
Luis