(8/11/2011) Keith Marvin - Re: Fwd: Re: follow upPage 1
From:
"Luis Pajares" <lpajares3@gmail.com>
To:
"Dean Dumke" <deand@JRJPaving.com>, "Coppell Keith Marvin" <kmarvin@copp...
Date:
12/14/2010 5:03 PM
Subject:
Re: Fwd: Re: follow up
Dean
I will meet you there at 7am.
Thanks
Luis
Luis
-----Original Message-----
From: "Dean Dumke" <deand@JRJPaving.com>
Date: Tue, 14 Dec 2010 16:32:35
To: Coppell Keith Marvin<kmarvin@coppelltx.gov>; <deand@JRJPaving.com>
Cc: <lpajares3@gmail.com>
Subject: RE: Fwd: Re: follow up
Luis,
I do not know of the area you are speaking about. I will be on site tomorrow morning at 7am if you can
meet me then. I have meetings at 7:30a at the Reserve, and a 9:30a and 1p in Allen. If 7a does not work,
please let me know what time you can.
Dean
Sent from my HTC Touch Pro2 on the Now Network from Sprint®.
-----Original Message-----
From: Keith Marvin <kmarvin@coppelltx.gov>
Sent: Tuesday, December 14, 2010 3:55 PM
To: deand@JRJPaving.com <deand@JRJPaving.com>
Cc: lpajares3@gmail.com <lpajares3@gmail.com>
Subject: Fwd: Re: follow up
Dean,
Please contact Mr. Pajares concerning final grading around his property. See his email below.
Thanks,
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> luis pajares <lpajares3@gmail.com> 12/14/2010 3:40 PM >>>
Keith
sorry to bother you with this, but this still needs to get done. they still
have not moved the dirt off all the trees. I spent most of saturday and
sunday moving the dirt, but ran out of gas. I do need them to get this
right. let me know if I need to walk it with you or with someone else.
thanks,
Luis
(8/11/2011) Keith Marvin - Re: Fwd: Re: follow upPage 2
On Wed, Dec 8, 2010 at 8:58 AM, Keith Marvin <kmarvin@coppelltx.gov> wrote:
> Luis,
>
> Attached is the claim form. This is to be filed with our City Secretary's
> office.
>
> I spoke with the contractor yesterday regarding the area on the back side
> of the retaining wall. They are aware of the work that needs to be done
> back there, and are schedule crews to be in here cleaning up over the next
> week.
>
> In order to move forward with the license agreement, I will need an exhibit
> that shows what you intend to do out there. I will then write the agreement
> and it will need to go to City Council for approval. As an example, I am
> attaching the agreement we took to City Council for Mr. Berkebile's property
> to your east.
>
> When do you think you will be ready to do the rock work on the roadway side
> of the wall? I'm trying to decide if I need to paint the concrete or leave
> it bare.
>
> Keith
>
>
> Keith Marvin, P.E.
> Project Engineer
> (972) 304-3681
>
>
>
> >>> luis pajares <lpajares3@gmail.com> 12/7/2010 9:35 AM >>>
> hi Keith,
> a couple of things:
> -can you please send me those forms you told us about? thanks.
> -we need to have the area behind the wall (our property side) cleaned up.
> they have not removed the concrete, rebarb and asphalt rubbish. also, they
> have not graded the dirt away from the tree roots, in fact they dumped more
> dirt on top of the post oaks. I spoke to one of the workers working out
> there, but he was disinterested. I can meet you out there to walk it if
> that helps.
> -what did we say were the next steps to get a license done?
>
> Please advise, thanks
> Luis
>
>