Keith Marvin - Bethel Rd - Slope fix
From: "Dean Dumke" <deand@JRJPaving.com>
To: "Keith Marvin" <kmarvin@coppelltx.gov>
Date: 12/22/2010 11:19 AM
Subject: Bethel Rd - Slope fix
Attachments:CO 122110 Ark Cont Quote BETHEL RD BRIDGE SHOTCRETE
PROTECTION.doc; CO 122210 Bethel Road-Alexander Court Flume Wall Preliminary
Bid Proposal.pdf
Keith,
Attached are the 2 quotes I received to fix the slope at the NW corner of the Bridge where it has eroaded from the
heavy rains. (Ark Contracting & TRW) If you approve one of these, I will then take the time to place in change
order format with an additional 10% as we did with the other stone wall.
Please let me know which you want or what I need to do so that we can continue to move forward. All indications
are that we will be complete next Wednesday. I will keep you informed.
Dean Dumke
Sr Project Manager
#469-223-7879
JRJ PAVING, L. P.
_______________________
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4D11DEABCity...8/11/2011
ARK CONTRACTING SERVICES, LLC.
420 SOUTH DICK PRICE ROAD
KENNEDALE, TEXAS 76060
OFFICE 817.478.7400 FAX 817.478.7438
December 20, 2010
JRJ Paving, Inc.
Attention: Dean Dumke
Re: Bethel Road Improvements
City of Coppell, Texas
Shotcrete Bridge Protection
Thank you for the opportunity to work with you on the above referenced project. Please
find enclosed our quote to install complete and in-place the following scope of work
listed below, in accordance with the attached concept drawings, and the listed exclusions
and clarifications as follows:
Item No. Description Quantity Unit Price Amount
1 Mobilization 1 LS $7,500.00 $ 7,500.00
2 Excavation (Rock) 125 CY $ 35.00 $ 4,375.00
3 Soil Nails 18 EA $ 500.00 $ 9,000.00
4 Rock Nails 87 EA $ 350.00 $30,450.00
5 Shotcrete 1,999 SF $ 10.00 $19,990.00
6 Earth Fill 125 CY $ 22.00 $ 2,750.00
7 18 Inch Rock RipRap 145 CY $ 85.00 $12,325.00
12 Structural Engineering 1 LS $7,500.00 $ 7,500.00
TOTAL PROJECT COST $ 93,890.00
Exclusions and Clarifications:
1.This proposal is based upon performing all work with 1 each mobilization.
2.Ark Contracting Services, LLC shall furnish sealed engineered shop drawings
prepared by a Professional Engineer registered in the State of Texas whom carries
a minimum of $1,000,000 errors and omissions insurance.
3.Suitable access, testing, barricade, traffic control and erosion control by others.
Page 1 of 2
Ark Contracting Services, LLC
.
420 South Dick Price Road
Kennedale, Texas 76060
12-20-2010
Bethel Road Bridge Gabion Protection
City of Coppell, Texas
Shotcrete Bridge Protection
4.No performance or payment bonds are included. Bonds can be furnished at cost
5.shall furnish valid certificates of insurance prior to
Ark Contracting Services, LLC
commencing work.
6.Monthly progress payments in the amount of (same percentage as per prime
contract) for work completed and materials delivered. All payments shall be due
within five (5) days of contractor’s receipt of payment. Payment to Ark
Contracting Services, LLC. for retainage shall be due within five (5) days of
contractor’s receipt of payment.
7.
This quote is good for thirty days from the date of the proposal.
Mark R. North
Ark Contracting Services, LLC.